On the directions of Hon’ble Supreme Court vide its order dated 10th December, 1996 passed in Civil writ Petition No 4677 of 1985, MC Mehta Vs Union of India, the Central Government had constituted the Central Ground Water Board as Authority vide notification number S.O. 38 (E), dated the 14th January, 1997 to exercise powers under sub section (3) of section 3 of the Environment (Protection) act, 1986 (29 of 1986) for the purposes of regulation and control of Ground Water Management and Development and to exercise certain powers and perform certain functions as per the said Act.
The Authority has been regulating ground water development and management by way of issuing ‘No Objection Certificates’ for ground water extraction to industries or infrastructure projects or Mining Projects etc., and framed guidelines in this connection from time to time applicable in twenty two States and two Union territories, where ground water development is not being regulated by the State Government and Union territory administration concerned.
To have sustainable management of water resources in the country groundwater abstraction guidelines have been prepared to regulate groundwater extraction and conserve the scarce groundwater resources in the country.
These guidelines will come into force with immediate effect from the date of Gazette Notification and will supersede all earlier guidelines issued by the Central Ground Water Authority (CGWA).
These guidelines will have pan India applicability. Ground water abstraction in States/ Uts (which are not regulating ground water abstraction) shall continue to be regulated by Central Ground Water Authority.
Further, wherever States/ Uts have come out with their own groundwater abstraction guidelines, which are inconsistent with the CGWA guidelines, the provisions of CGWA guidelines will prevail. However, in case the guidelines followed by such States/ Uts contain some more stringent provisions than CGWA guidelines, such provisions may also be given effect to by the States/ Uts Authorities in addition to those contained in the CGWA guidelines. States may be at liberty to suggest additional conditions/ criteria based on the local hydro-geological situations which shall be reviewed by CGWA/Ministry of Jal Shakti, Government of India before acceptance.
All new/existing industries, industries seeking expansion, infrastructure projects and mining projects abstracting ground water, unless specifically exempted under Para 1.0 below, will be required to seek No Objection Certificate from Central Ground Water Authority or, the concerned State/ UT Ground Water
35
Authority as the case may be. The entire process of grant of No Objection Certificate shall be online through a web based application system.
Water management plans shall be prepared by all the State Ground Water Authorities/ Organizations for all Over-exploited, Critical and Semi-critical assessment units starting with Over-exploited units. Water management plans shall be reviewed and updated periodically. Water management plans, data on water availability and scarcity and policy framed in this regard shall be placed on the websites of Central Ground Water Authority/ State Ground Water Authority.
1.0 Exemptions from seeking No Objection Certificate:
Following categories of consumers shall be exempted from seeking No Objection Certificate for ground water extraction:
(i) Individual domestic consumers in both rural and urban areas for drinking water and domestic uses.
(ii) Rural drinking water supply schemes.
(iii) Armed Forces Establishments and Central Armed Police Forces establishments in both rural and urban areas.
(iv) Agricultural activities.
(v) Micro and small Enterprises drawing ground water less than 10 cum/day.
1.1 Registration of Drilling Rigs
State / Ut Governments shall be responsible for registering drilling rigs operating within their jurisdiction and for maintaining the database of wells drilled by them. Appropriate link shall be provided in CGWA portal for making the data available to CGWA.
2.0Drinking & Domestic use for Residential apartments/ Group Housing Societies/ Government water supply agencies in urban areas
For grant of No Objection Certificate for ground water extraction, the project proponent has to furnish the details as per the guidelines issued by the CGWA in proper format as available in CGWA website. No Objection Certificate for new /existing wells shall be granted only in such cases where the local Government water supply agency is unable to supply requisite amount of water in the area.
No Objection Certificate shall be granted subject to the following specific conditions:
i) Installation of Sewage Treatment Plants shall be mandatory for all residential apartments/ Group Housing Societies where ground water requirement is more than 20 m3/day. The water from Sewage Treatment Plants shall be utilized for toilet flushing, car washing, gardening etc.
ii) The No Objection Certificate shall be valid for a period of five years from the date of issue or till such time local Government water supply is provided to the project area, whichever is earlier. In case the project proponent receives water supply from the concerned local Government Water Supply Agency during the validity of the No Objection Certificate, intimation regarding availability of public water supply shall be sent by the project proponent to CGWA and No Objection Certificate will be cancelled by the Authority. In other cases, the project proponent will apply for renewal of No Objection Certificate, ninety days before the expiry of No Objection Certificate.
iii) Proponents shall be liable to pay ground water abstraction charges for the quantum of ground water proposed to be extracted, as per rates mentioned in Table 5.1.
a) Details of water requirement computed as per National Building Code, 2016 (Annexure I), taking into account recycling/ reuse of treated water for flushing etc.
b) Affidavit on non-judicial stamp paper of Rs. 10/- by the applicant, confirming non/ inadequate availability of public water supply in case of users requiring ground water up to 1 0 m 3 / day for drinking/ domestic use.
c) Certificate of non-availability of water from local government water supply agency in cases requiring ground water in excess of 1 0 m 3 / day for drinking/ domestic use. Government water supply agencies
[PART II—SEC. 3(ii)]
applying for No Objection Certificate shall submit copy of government approval of the scheme/ project proposed to be implemented.
d) Ground water quality data of existing bore well/ tube well/ dug well from any National Accreditation Board for Testing and Calibration Laboratories (NABL) accredited laboratory or Govt. approved laboratory (in case of existing projects applying for no objection certificate)
e) Proposal for rain water harvesting/ recharge within the premises as per Model Building Bye Laws issued by Ministry of Housing & Urban Affairs.
Annexures
Annexure I: Estimation of water requirements for drinking and domestic use.
Annexure II: Guidelines for construction of piezometers and monitoring of groundwater levels and quality.
Annexure III: Measures to be adopted to ensure prevention from pollution in the plant premises of polluting industries/ projects.
Annexure IV: Outline of hydro-geological report for obtaining No Objection Certificate for industries.
Annexure V: Format of the Report on ground water conditions (for mining projects).
Annexure VI: Indicative list of Infrastructure projects.
Annexure VII: Supreme Court Order in Civil Writ petition 36 of 2009 regarding measures for prevention of fatal accidents of small children due to their falling into abandoned bore wells and tube wells.
Annexure VIII: List of States/ Union territories where ground water extraction is being regulated by Central Ground Water Authority (CGWA)
Annexure IX: Glossary of technical terms used
Annexure X : Annual water audits by the industries Guidelines to regulate and control groundwater extraction in India
Ministry of JAL Shakti
CGWA Guidelines to Regulate and Control Groundwater Extraction 2020
2020 · PDF page 1
Hover any section to copy its link or text, ask Copilot about it, or bookmark it.
(Department Of Water Resources, River Development And Ganga Rejuvenation) (CENTRAL GROUND WATER AUTHORITY)
NOTIFICATION
New Delhi, the 24th September, 2020
S.O. 3289(E).—WHEREAS, on the directions of Hon’ble Supreme Court vide its order dated the10th December, 1996 passed in Civil writ Petition No 4677 of 1985, MC Mehta Vs Union of India, the Central Government constituted the Central Ground Water Authority (hereafter referred to as the ‘Authority’) vide notification number S.O. 38 (E), dated the 1 4 t h January, 1997 to exercise powers under Section 5 of the Environment (Protection) act, 1986 (29 of 1986) for the purposes of regulation and control of Ground Water management and development and to exercise certain powers and perform certain functions relating thereto;
AND WHEREAS, the Authority has been regulating ground water development and management by way of issuing ‘No Objection Certificates’ for ground water extraction to industries or infrastructure projects or Mining Projects etc., and framed guidelines in this connection from time to time in twenty two States and two Union territories, where ground water development is not being regulated by the State Government Union Territory administration concerned;
4.1Industrial Use
In Over-exploited assessment units, No Objection Certificate shall not be granted for ground water abstraction to any new industry except those falling in the category of Micro, Small and Medium Enterprises (MSME). However, No Objection Certificate for drinking/ domestic use for work force, green belt use by these new industries shall be permitted. Expansion of existing industries involving increase in quantum of ground water abstraction in over-exploited assessment units shall not be permitted. No Objection Certificate shall not be granted to new packaged water industries in Overexploited areas, even if they belong to MSME category.
No Objection Certificate for ground water extraction by industries shall be granted subject to the following specific conditions:
i) No Objection Certificate shall be granted only in such cases where local government water supply agencies are not able to supply the desired quantity of water.
ii) All industries shall be required to adopt latest water efficient technologies so as to reduce dependence on ground water resources.
iii) All industries abstracting ground water in excess of 100 m3/d shall be required to undertake annual water audit through Confederation of Indian Industries (CII)/ Federation Indian Chamber of Commerce and Industry (FICCI)/ National Productivity Council (NPC) certified auditors and submit audit reports within three months of completion of the same to CGWA. All such industries shall be
37
required to reduce their ground water use by at least 20% over the next three years through appropriate means.
iv) Construction of observation well(s) (piezometer)(s) within the premises and installation of appropriate water level monitoring mechanism as mentioned in Section 15 shall be mandatory for industries drawing/ proposing to draw more than 10 m3/day of ground water and. Monitoring of water level shall be done by the project proponent. The piezometer (observation well) shall be constructed at a minimum distance of 15 m from the bore well/production well. Depth and aquifer zone tapped in the piezometer shall be the same as that of the pumping well/ wells. Detailed guidelines for design and construction of piezometers are given in Annexure II. Monthly water level data shall be submitted to the CGWA through the web portal.
v) The proponent shall be required to adopt roof top rain water harvesting/ recharge in the project premises. Industries which are likely to pollute ground water (chemical, pharmaceutical, dyes, pigments, paints, textiles, tannery, pesticides/ insecticides, fertilizers, slaughter house, explosives etc.) shall store the harvested rain water in surface storage tanks for use in the industry.
4.2Mining Projects
All existing as well as new mining projects will be required to obtain No Objection Certificate for ground water abstraction. Since mining projects are location specific, there will be no ban on grant of No Objection Certificate for abstraction of ground water for such projects in over-exploited assessment units.
No Objection Certificate for mining projects shall be granted subject to the following specific conditions:
i) It shall be mandatory for all the mining industries to ensure that water available from de-watering operations is properly treated and should be gainfully utilized for supply for irrigation, dust
[PART II—SEC. 3(ii)]
suppression, mining process, recharge in downstream and for maintaining e-flows in the river system.
ii) Construction of observation well(s) (piezometers) along the periphery in the premises, for monthly ground water level monitoring, shall be mandatory for mines drawing/ proposing to draw more than 10 m3/day of ground water. Depth and aquifer zone tapped in the piezometer shall be commensurate with that of pumping well/ wells.
iii) In addition, the proponent shall monitor ground water levels by establishing observation wells (piezometers) in the core and buffer zones as specified in the No Objection Certificate.
iv) In case of coal and other base metal mining the project proponent shall use the advance dewatering technology (by construction of series of dewatering abstraction structures) to avoid contamination of surface water.
v) In addition to this, all mining units shall also monitor the water quality of mine seepage and mine discharge through NABL accredited/ Govt. approved laboratories and the same shall be submitted at the time of self compliance.
vi) All mining projects drawing ground water in safe, semi-critical and critical assessment units shall be required to pay ground water abstraction charges as applicable as per Tables 5.4 A.
vii) All mining projects drawing ground water in over-exploited assessment units shall be liable to pay ground water restoration charges as per Table 5.4 B.
(a) Mining plan approved by the concerned Govt. agency/ department.
(b) Proposal for rain water harvesting/ recharge within the premises as per Model Building Bye Laws issued by Ministry of Housing & Urban Affairs.
(c) Comprehensive report prepared by accredited consultant on ground water conditions in both core and buffer zones of the mine, depth wise and year wise mine seepage calculations, impact assessment of mining and dewatering on ground water regime and its socio-economic impact, details of recycling, reuse and recharge, reduction of pumping with use of technology for mining and water management to minimize and mitigate the adverse impact on ground water, based on local conditions. Format for report is given in Annexure V.
4.0Commercial Use
No new major industries shall be granted No Objection Certificate in over-exploited assessment areas except as per the policy guidelines.
Availability of ground water resources shall be given due regard while considering applications for grant of No Objection Certificate for commercial use.
Commercial entities extracting ground water shall be required to submit online annual water audit report including an audit of water use as mentioned in the relevant sections. CGWA/ State Ground Water Authority (SGWA) shall publish all such audit reports online.
CGWA/ SGWAs shall engage independent agencies to verify the compliance of No Objection Certificate conditions periodically.
AND WHEREAS, some of the State Governments or, Union territories enacted legislations and issued regulatory directions or orders for regulating ground water development and management;
AND WHEREAS, the Hon’ble National Green Tribunal, New Delhi vide order dated the 1 5 t h April 2015 in OA Nos. 204/205/206 of 2014 has issued directions to the Authority to ensure that any person operating tube-well, or any means to extract ground water shall obtain permission from the Authority and shall operate the same subject to the law in force, even if such unit is existing unit or the unit is yet to be established;
AND WHEREAS, the said Hon’ble Tribunal vide its order dated the 0 9 t h July, 2015 in OA Nos. 34 and 37 of 2014 directed all industrial units which are members of the Common Effluent Treatment Plants (CETPs) to approach the Authority through State Pollution Control Board for obtaining ‘No Objection Certificate’ in accordance with the law;
AND WHEREAS, the aforesaid Hon’ble Tribunal vide order dated the 1 3 t h July, 2017 in OA No 200- of 2014 directed that every industry should be directed to pay for extraction of such water, that too, subject to the conditions stated in the order permitting such extraction;
AND WHEREAS, the said Hon’ble Tribunal vide its order dated the 2 8 t h August, 2018 in O.A. Nos. 176 of 2015 and 59 of 2012 respectively directed the Ministry of Water Resources, River Development and Ganga Rejuvenation to forthwith review the existing mechanism so as to ensure effective steps for conserving the groundwater resources;
AND WHEREAS, in pursuance of the directions of the Hon'ble National Green Tribunal and powers conferred by sub-section (3) of section 3 and section 5 of the Environment (Protection) Act, 1986 the Authority, with a view to protect the ground water resources had circulated the draft guidelines for grant of ‘No Objection Certificate’ on the 1 1 t h October, 2017 inviting comments and suggestions from all the stakeholders;
AND WHEREAS, all objections and suggestions received in response to the said draft guideline have been duly considered by the Central Government, the Authority notified the guidelines to regulate groundwater over-exploitation and to conserve the groundwater resources in the country vide notification number S.O. 6140 (E), dated the 1 2 t h December, 2018;
AND WHEREAS, the aforesaid Hon’ble Tribunal vide order dated the 0 3 r d January 2019 in the OA No. 176 of 2015 directed that the above mentioned notification dated the 1 2 t h December, 2018 may not be given effect to as it is unsustainable if tested on ‘Precautionary Principle, Sustainable development as well as Inter-generational Equity Principles’ and if implemented, will result in fast depletion of groundwater and damage to water bodies and will be destructive of the fundamental right to life under Article 21 of the Constitution of India;
AND WHEREAS, the said Hon’ble Tribunal vide order dated the 1 1 t h September, 2019 constituted a committee to deliberate on steps for preventing depletion of groundwater, robust monitoring mechanism
33
against unauthorised extractions and fulfillment of ‘No Objection Certificate’ conditions, environment compensation etc and to submit a report;
AND WHEREAS, the aforesaid committee submitted the report along-with draft guidelines to regulate groundwater extraction and groundwater conservation in Hon’ble Tribunal on the 16th March, 2020;
AND WHEREAS, the above said Hon’ble Tribunal vide order dated the 20th July, 2020 directed to comply with certain points for sustainable groundwater management while issuing ‘No Objection Certificates’ to commercial establishments by the Authority;
Now therefore, in pursuance of the directions of Hon’ble National Green Tribunal and the powers conferred by sub-section (3) of Section 3 read with Section 5 of the Environment (Protection) Act, 1986 (29 of 1986), the Department of Water Resources, River Development & Ganga Rejuvenation, hereby notifies the guidelines to regulate and control groundwater extraction in the country in supersession to this Ministry notification vide S.O. 6140 (E), dated the 1 2 t h December, 2018 as per the Schedule below:
SCHEDULE
Guidelines to regulate and control ground water extraction in India (with immediate effect)
ITEM Page No.
Preamble and Background
1.0 Exemptions from seeking No Objection Certificate....35
2.0 Drinking & Domestic use for Residential apartments/ Group Housing Societies/ Government water supply agencies in urban areas....35
3.0 Agriculture Sector....36
4.0 Commercial Use....36
4.1 Industrial Use....36
4.2 Mining Projects....37
4.3 Infrastructure projects....38
5.0 Ground water abstraction/ restoration charges....39
5.1 Rates of Ground water abstraction /restoration charges....40
6.0 Bulk Water Supply....42
7.0 Abstraction of Saline ground water....42
8.0 Protection of Wetland Areas....42
9.0 General compliance conditions in No Objection Certificate....43
10.0 Monitoring of compliance of No Objection Certificate Conditions....43
11.0 Renewal of No Objection Certificate....44
12.0 Extension of No Objection Certificate....44
13.0 Delegation of powers against illegal groundwater withdrawal....44
14.0 Ground Water Level Monitoring....45
15.0 Environmental Compensation....45
15.1 Rates of Environmental Compensation:....45
15.2 Deterrent Factors to compensate losses and environmental damage (for packaged drinking water units, mining, industries and infrastructural dewatering projects)....46
16.0 Provision of Penalty....46
17.0 Other important Conditions (Applicable to all):....48
[F. No. CGWA-21/4/2020-CGWA]
ASHISH KUMAR, Director
[PART II—SEC. 3(ii)]
vi) Injection of treated/ untreated waste water into aquifer system is strictly prohibited.
vii) Industries which are likely to cause ground water pollution e.g. Tanning, Slaughter Houses, Dye, Chemical/ Petrochemical, Coal washeries, other hazardous units etc. (as per CPCB list) need to undertake necessary well head protection measures to ensure prevention of ground water pollution (Annexure III).
viii) All industries drawing ground water in safe, semi-critical and critical assessment units shall be required to pay ground water abstraction charges as applicable as per Tables 5.2 A and 5.3 A.
ix) All existing industries drawing ground water in over-exploited assessment units shall be liable to pay ground water restoration charges as applicable as per Tables 5.2 B and 5.3 B.
(a) An affidavit on non judicial stamp paper of Rs. 10/- regarding non availability of water supply from local government agencies in cases where ground water requirement is up to 10 m3/day.
(b) Certificate regarding non/ partial availability of fresh water/ treated waste water supply from the local government water supply agency in cases where requirement of ground water is more than 10 m3/day.
(c) Ground water quality data of existing bore well/ tube well/ dug well from any NABL accredited laboratory or Govt. approved laboratory (in case of existing projects applying for No Objection Certificate)
(d) Water quality data of bore well/ tube well/ dug well in respect of existing industries from NABL accredited laboratories/Government approved laboratories.
(e) Proposal for rain water harvesting/ recharge within the premises as per Model Building Bye Laws issued by Ministry of Housing & Urban Affairs.
(f) Impact Assessment report: All projects extracting/proposing to extract ground water in excess of 100 m3/day in Over-exploited, Critical and Semi-critical areas shall have to mandatorily submit impact assessment report of existing/ proposed ground water withdrawal on the ground water regime and also socio-economic impacts report prepared by accredited consultants. Pro-forma for the report is given in Annexure IV.
3.0Agriculture Sector
Agriculture sector is the backbone of the Indian economy. As per Minor Irrigation Census 2013-14, 87.86% of wells are owned by marginal, small and semi-medium farmers having land holding up to 4 hectares (ha). Around 9.18 % of wells are owned by medium farmers having land holding 4 – 10 ha and 2.96% of the wells are owned by big farmers having land holding more than 10 ha.
Considering the number of ground water abstraction structures, regulation of ground water in agriculture sector through a ‘command and control’ strategy will prove to be an arduous task. Therefore, a participatory approach for sustainable ground water management would be more productive.
States/Uts are advised to review their free/subsidized electricity policy to farmers, bring suitable water pricing policy and may work further towards crop rotation/diversification/other initiatives to reduce overdependence on groundwater.
Agriculture sector shall be exempted from obtaining No Objection Certificate for ground water extraction.