2.1.3 Construction Phase
2.1.3.1 Organizational structure
The site management should be carried out through suitable site organization structure with roles and responsibilities assigned to the construction personnel for various construction related functions. Safety management is one of the important components of site management.
2.1.3.2 Site layout
The layout of the construction site should be carefully
planned keeping in view the various requirements to construction activities and the specific constraints in terms of its size, shape, topography, traffic and other restrictions, in public interest. A well planned site layout would enable safe smooth and efficient construction operations. The site layout should take into considerations the following factors:
a) Easy access and exit, with proper parking of vehicle and equipments during construction.
b) Properly located material stores for easy handling and storage.
c) Adequate stack areas for bulk construction materials.
d) Optimum location of plants and equipments (batching plants, etc).
e) Layout of temporary services (water, power, power suppression unit, hoists, cranes, elevators, etc).
f) Adequate yard lighting and lighting for night shifts.
g) Temporary buildings; site office and shelter for workforce with use of non-combustible materials as far as possible including emergency medical aids.
h) Roads for vehicular movement with effective drainage plan.
j) Construction safety with emergency access and evacuations and security measures.
k) Fabrication yards for reinforcement assembly, concrete precasting and shuttering materials.
m) Fencing, barricades and signages.
2.1.3.3 Access for fire fighting equipment vehicles
Access for fire fighting equipment shall be provided to the construction site at the start of construction and maintained until all construction work is completed.
2.1.3.3.1 Free access from the street to fire hydrants/ static water tanks, where available, shall be provided and maintained at all times.
2.1.3.3.2 No materials for construction shall be placed within 3 m of hydrants/static water tanks.
2.1.3.3.3 During building operations, free access to permanent, temporary or portable first-aid fire fighting equipment shall be maintained at all times.
2.1.3.4 Access to the upper floors during construction
In all buildings over two storeys high, at least one stairway shall be provided in usable condition at all times. This stairway shall be extended upward as each floor is completed. There shall be a handrail on the staircase.
2.1.3.5 Construction strategy and construction sequence
Construction strategy and construction methods are to be evolved at the planning and design stage specific to the conditions and constraints of the project site and implemented by the site management personnel to ensure ease of construction and smooth flow of construction activities. Sites of high water table conditions with aggressive chemical contents of subsoil needs special design considerations. Buildings with basement in sites of high water table should be planned with dewatering scheme with appropriate construction sequence. Duration of dewatering should continue till sufficient dead loads are achieved to stabilize the buoyancy loads with adequate factor of safety. The construction sequence should be planned taking into consideration the following aspects:
a) Availability of resources (men, material and equipment);
b) Construction methods employed including prefabrication;
c) Planned construction time;
d) Design requirements and load transfer mechanism;
e) Stability of ground like in hilly terrain;
f) Ensuring slope stability with retaining structure before the main construction;
g) Installation and movement of heavy equipments like cranes and piling equipments;
h) Effect of weather; and
j) Minimum time to be spent below ground level working.