The NIMZs are important instrumentality of the National Manufacturing Policy. The NIMZs are envisaged as integrated industrial townships with land use on the basis of zoning, clean and energy efficient technology, necessary social infrastructure, skill development facilities etc. to provide a productive environment for persons transitioning from the primary to the secondary and tertiary sectors.
The key features of the NIMZ Guidelines are:
- The approval process is in two stages: In principal approval and final approval for the NIMZ. After the in-principal approval, as soon as a substantial part of the land area is in possession of State Government, application for obtaining final approval shall be made which will be granted at the level of Ministry of Commerce and Industry.After obtaining the approval, each NIMZ will be notified by the DIPP in the official gazette.
a. For planning the NIMZ, maps shall be prepared and submitted along with the application for final approval. The maps shall consist of following:
Administrative and physical map: indicating the districts, villages, townships, water bodies, high lands, low lands and forests etc. which are located within its boundaries.
Existing land use map: At least 30% of the total land area proposed for the NIMZ will be utilized for location of manufacturing units.
External and existing internal linkages map of proposed NIMZ.
b. Preparation of Techno-economic feasibility report cum development plan and presentation by the State for final approval. It shall include the following:
Overview of the region and adjoining areas
External linkages
Existing internal infrastructure in NIMZ area
Land including status and time frame of land acquisition
– Assessment of industrial and commercial potential
Preliminary environment impact assessment
External and technical infrastructure requirement
Financial implications
Proposed management structure
Zone development plan
– Regulatory environment
a. Constitution of Special Purpose Vehicle to discharge the functions: There shall be a provision for suitable representation of a nominee of the Government of India (DIPP), and of the allottees and subsequently of the industrial units on the Board of the SPV.
b. Preparation of Master Plan and designing by SPV
c. Preparation of a strategy of development of zone and action plan for self-regulation within 3 months from constitution of SPV.
-
Land Allotment: Land shall be allotted on leasehold basis by SPV. The SPV will ensure that land is utilised as per the permissible purpose within the specified period of time as indicated in the land allotment letter otherwise, it shall revert back to the SPV.
-
Land for NIMZs: NIMZs would be large developed land, with the requisite eco-system for promoting world class manufacturing activity. They would be different from SEZs in terms of size, level of infrastructure planning, and governance structures related to regulatory procedures and exit policies. Following are the land requirements for NIMZ:
a. Size of land for NIMZ – An NIMZ would have an area of at least 5000 hectares in size.
b. Availability of land- The State Government will be responsible for selection of land suitable for development of the NIMZ including land acquisition, if necessary. The land may constitute:
i. Government owned land;
ii. Private lands falling within the proposed NIMZ, to be acquired by the State Government;
iii. Land under existing industrial areas/estates/sick and defunct units including PSUs.
Following guiding principles will be applied by the State Government for the purpose of acquiring land for NIMZ sites:
i. Preferably in waste lands; infertile and dry lands not suitable for cultivation;
ii. Use of agricultural land to the minimum;
iii. All acquisition proceedings to specify a viable resettlement and rehabilitation plan;
iv. Reasonable access to basic resources like water;
v. It should not be within any ecologically sensitive area or closer than the minimum distance specified for such an area.
5. Rationalisation and simplification of regulatory processes:
High priority shall be given to Environment Clearance under EIA Notification, 2006
The entire process of clearances by State authorities will be made web-enabled.
Timelines will be defined in respect of all clearances and there is provision of deemed approval of clearances.
a. Bearing the cost of Master Planning
b. Provision of external infrastructure: Creation/ Up gradation of external infrastructure through PPP and provision of Viability gap funding through existing schemes
c. Provisions for creation of internal infrastructure:
i. Through Viability Gap Funding (VGF): Supporting Public Private Partnerships in infrastructure (maximum twenty percent of the total project cost).
ii. Long term soft loans from multilateral financial institutions
iii. External commercial borrowings
-
Set up of Technology Acquisition and Development Fund for creation of a patent pool; incentivization of production of environment friendly machines/ equipment and of SMEs for adoption of environmental audit, water audit and waste water treatment practices.
-
Provision of institutional infrastructure for productivity, quality (testing facilities etc.) and design capabilities, encouraging innovation and skill development within the NIMZ.
-
Funding for establishment of an ITI on Built Own Operate basis by the SPV in NIMZ.
-
Provision of VGF for setting up specialised polytechnics for relevant industry verticals in a NIMZ