4.2Procedure for submitting application through self-certification:
(a)Any person intending to erect or re-erect building shall apply on Form BCS-I along with documents stated in Code 4.1 to the competent authority for approval of building plans of buildings falling in low and moderate risk categories defined in Code 6.2 (i) and 6.2(ii), under self-certification to the competent authority for
intimation. The applicant may initiate construction immediately after submission of the application and documents.
(b)Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in the relevant Form BCS-II.
(c)Competent Authority or any other authorized person reserves the right to check the building plans and construction at any stage and violations (except compoundable ones), if found shall have to be rectified by the owner/applicant. In case the owner/ applicant fails to rectify violations, the Competent Authority shall be intimated to take necessary steps to remove the violations within a stipulated time, as decided by the Approval Authority(ies). In case of failure to do so by architects, the case shall be referred to Council of Architecture, who may impose penalties as may deemed necessary. In case of failure by other competent authorities, the penalty shall be as imposed by local court. All rectifications shall be at the risk and cost of the owner and no plea of the owner shall be entertained for any default committed by the competent authority engaged by the owner. In all such cases the procedure of self- certification shall stand nullified.
(d)If a building is erected or re-erected or construction work is commenced in contravention to any of the applicable provisions of the Bye-Laws, the competent authority or any other person authorized by it shall be competent to require the building to be altered or demolished, by a written notice delivered to the owner. Such notice shall also specify the period during which such alteration or demolition shall be completed and if the notice is not complied with, the competent authority or any other person authorized by it may demolish the said building at the expense of the owner.
Note: - The decision of competent authority, in case of any dispute shall be final and binding on all concerned.
(e)At any stage during construction, if an architect notices that violations (except sanctionable ones) are taking place, he shall intimate to the concerned authority of such violations and stop further supervision. He/she shall also intimate the allottee about the violations and advise him to stop further construction. Complete details along with photographs shall be submitted to the concerned authority. The competent authority shall immediately issue a notice to the owner based on the architect’s certificate to suspend further work and rectify violations. In such cases the owner shall be held responsible for further additions in violations. Such a situation shall automatically annul the process of self-certification and the owner may, after removal of violations, engage an architect for preparing the revised drawings. In such cases completion shall be given only after scrutiny of revised drawings and inspection of site.
(f) Sanctionable changes shall be allowed, provided that at the completion stage all changes are incorporated by the architect in the completion drawings to be submitted by the owner to the competent authority. While seeking occupation certificate, the architect shall give a certificate that all changes are made as per Bye-Laws and or directions issued from time to time.
(g)After submission of the building application and or during the construction of building, if the owner changes the architect/structural engineer, shall intimate the competent authority by email or online building plan approval system and also the architect/structural engineer shall intimate the competent authority that he is no longer responsible for the project from the date of actual dispatch of the letter. The information must be sent within seven (7) days of occurrence of the change. The construction work shall have to be suspended until the new owner/architect/structural engineer, as case may be, undertakes the full responsibility of the project as per the forms and documents submitted at the time of applying for erection/re- erection of the building within seven (7) days of his taking over. Owner’s intimation regarding change of name of professionals shall be considered final by the competent authority or any other person authorized by it.
4.3Online receipt and approval.
(a) All functions performed under these building Bye-Laws be performed through electronic form.
(b) Without prejudice to the generality of Code 4.2 (a), the functions shall include all or any of the following:
i. receipt or acknowledgement of application and payment,
ii. issue of approvals, orders, or directions,
scrutiny, enquiry, or correspondence for approval of building plans or grant of occupation certificates, etc.,
iv. filing of documents,
v. issue of notices for recoveries,
vi. maintenance of registers and records,
vii. any other function that the competent authority may deem fit in public interest.
4.4 Preparation of Government building plans by Government Department (s)
The Government Departments preparing the building plans for the government buildings conforming to these Building Bye-Laws, shall issue a certificate specifying that the provisions of these Building Bye-Laws have been adhered to in all respects. Such plans shall be sent to the competent authority, for information and records before the commencement of erection or re-erection of the building(s).
4.5Constitution of committees comprising officials of Municipal body and of the Authority
The competent authority shall constitute a committee or committees to perform the following functions:
(i) preparation of zoning plans,
(ii) approval of building plans,
(iii) composition of violations of building plans,
(iv) grant of occupation certificate,
(v) joint inspection, and
(vi) any other committee with such powers and functions, as may deem proper
Relevant timelines shall be determined for approval, inspection or grant of occupation certificate as decided by the competent authority. The committee shall comprise of officials from Municipal Committees, Ladakh Autonomous Hill Development Council, Tourism Department, Pollution Control Committee, Ladakh Heritage Commission, Himalayan Institute of Alternatives, Ladakh (indicative).
4.6 Submission of affidavit
The Competent Authority at the stage of approval of building plans, DPC level or grant of occupation certificate, if requires, case to case basis, may ask for an affidavit from the applicant, as per standard format given at Annexure-A.
4.7Building Drawing Norms
a) Size of drawing sheets and colouring of plans:
(i) The size of drawing sheets shall be any of those specified as below:
Sr. No.
Sheet name
Sheet size (in mm)
1
A0
841 x 1189
2
A1
594 x 841
3
A2
420 x 594
4
A3
297 x 420
5
A4
210 x 297
(ii) All dimensions in plan shall be indicated in metric units.
(iii) Various elements of plans (site and building), elevation, section and details shall be shown in different colors and thickness/type of line, etc., and shall be preferably prepared in layers and as per these Bye-Laws.
(iv) The prints of drawings shall be on one side of the paper only.
b) Key Plan: A key plan drawn to a scale of not less than 1: 10,000 shall be submitted along with notice showing boundary and location of the site with respect of neighborhood landmarks, in area where there are no approved layout plans.
c) Site Plan:
(i) The site plan to be submitted along with the application for seeking permission shall be drawn to a scale of:
1:100 for plots up to 500 square meters in size and
on a scale of 1:500 for plots up to 1 acre in size, and
for plots above one acre in size the site plan may be submitted at any readable scale.
(ii) The plan shall indicate the following details:
boundaries of the site and any contiguous feature, including but not limited to buildings up to 60 feet in surrounding areas,
position of the site in relation to the neighbouring street/revenue rasta,
name (s) and width of the street (s) on which the site is situated, if any,
all existing buildings standing on, over or under the site,
position of the building and of all other buildings, if any, which the applicant intends to erect upon his contiguous land referred to in (i),
means of access from the street to the building, and to all other buildings, if any which the applicant intends to erect upon his contiguous land, referred to in (i),
4.8Clearance zone for buildings near/adjoining High Tension Lines electricity (Distance from Electric lines NBC Part 3 Code 6.4)
No building or part thereof including Projections from the face of the outer walls shall be allowed to be erected or re-erected or any addition or alteration made to a building within the distances quoted below in accordance with the current Indian Electricity Rules as amended from time to time between the buildings and any overhead electric supply line
Type of High voltage Electricity Lines
*Vertical
**Horizontal clearance (in meters)
a.
Low and medium Voltage and service lines,
2.5
1.2
b.
High Voltage lines up to and including 11 KV lines,
3.7
1.2
c.
High Voltage lines above 11 KV and up to and including 33 KV.
3.7
2.0
d.
Extra High voltage lines beyond 33 KV
3.7 (Plus 0.3 meters for very additional 33 KV or part thereof)
2.0 (Plus 0.3 meters for very additional 33KV or part thereof)
e.
* The horizontal clearance shall be measured when the line is at a maximum deflection from the vertical due to wind pressure. ** The horizontal clearance between the nearest conductor and any part of such building shall, on the basis of maximum deflection due to wind pressure, be not less than as given above
Also See Part VIII, Rules 77 to 80 of The Indian Electricity Rules, 1956
Chapter 4Plan Application Procedures
4.1 Application for erection or re-erection of building
(a) Any person who intends to erect, re-erect or make alternation in a building or demolish any building shall give notice in writing to the competent authority in the Form BC-I, accompanied by the following documents:
i. Ownership documents-lease deed/sale deed, proof of ownership certified by the revenue authority (Jamabandi) in the case of self-owned property and in the case of a plot allotted by the authority copy of the allotment letter and of the possession letter in the name of owner issued by the allotment authority, and a copy of the letter in the case where permission to use the land for the intended purpose issued by the competent authority,
ii. Every person who intends to erect, re-erect or make alternation in any place in a building or demolish any building shall give notice in writing to the Authority of his intention in the prescribed Form BC-I, as per Annexure – A and such notice shall be accompanied by plans and statements in sufficient copies. The plans may be ordinary prints on ferro-paper or any other type, one set of which shall be laminated. One set of such plans shall be released, and the rest retained in the office of the Authority for record after the issue of permit or refusal as the case may be.
iii. Online portal for auto-scrutiny shall always require upload of the recommended digital format of the drawings to be uploaded on the portal for use; the provision of submission, of drawings and auto-scrutiny shall be formulated by UT Administration/Local bodies or any such bodies as appointed by UT Administration/Local bodies and shall have the purview of the same. These may include but not be limited to built features, coverage and features, coverages, setbacks, provisions for universal design, parking, mezzanine, building distances, heights, chimneys, parapets, mumties, fire management, exemptions, green rating applications, access, etc.
iv. a site plan as required under these Building Bye-Laws Section 3.122,
v. details of specifications of the work to be executed in Form BC-II,
vi. Structural drawings, for record, as per Form BC-V(A1) or BC-V(A2),
vii. Fire safety design as required under Part IV of the National Building Code and as updated/revised from time to time in the case of buildings more than 15 meters in height and all non-residential buildings.
viii. Heating, ventilation, air-conditioning (H.V.A.C.) service plan wherever required,
width of the street, in front, and or on the sides or rear of the site, if any,
direction of the north point relative to the plan of the buildings,
any existing physical feature(s) such as well, drains, trees, overhead/underground electricity lines including its voltage/capacity, etc.,
service connection details with any critical infrastructure details including but not limited to drains, overhead/underground electricity lines including its voltage/capacity, etc.
area of the site, proposed covered area on each floor, and covered area percentile to the total area of the site,
plot number or revenue particulars of the property on which the building is intended to be erected,
graphical scale with north direction,
parks, landscape plans, parking plans and contour plans surrounding the land, and
such other details as may be prescribed by the competent authority.
ix. Plumbing drawings, water supply drawings and toilet drawings
x. Certificate of conformity with these Bye-Laws and structural safety for the relevant buildings (depending upon type and height) in the relevant Form BC- V(A1) or BC-V(A2),
xi. Public health services plan in un-editable compact disc/DVD or any
other electronic medium, containing drawings in “DWG” Format,
xii. A person applying for permission to carry out any development shall have to pay tree plantation deposit along with his application to the Competent Authority at the rates decided by the Competent Authority time to time. This deposit shall be refundable after the period of five years with the condition that trees planted on the site shall be grown‐up and maintained properly, otherwise the deposit shall be forfeited and shall be utilized only for tree plantation and maintenance by the Competent Authority.
xiii. Scrutiny fees (nonrefundable) at the rate of ten (10) rupees per square meter for the proposed aggregated construction area to be achieved including basement, stilt floor, service floor and mezzanine, to be deposited in favour of the competent authority through any prescribed payment mode.
xiv. No objection certificate from the Authority regarding land use as per Master/Zonal Plan, if required.
xv. Approval from the Chief Inspector of Factories in case of Industrial Buildings; as well as from the Pollution Control Board, wherever required
xvi. Approval from Chief Controller of Explosives in case of Industrial Buildings; as well as from the Pollution Control Board, wherever required
xvii.Indemnity Bond in case of proposal for the construction of a basement as given in Annexure – ‘B-1’
xviii. Approval from Chief Fire Officer, or any other authority as appointed by UT Administration, in case of building defined under Code 3.22 shall be required
xix. No-objection certificate from Civil Aviation Department wherever required by competent authority
xx. No-objection certificate from relevant Defense Authority, wherever required by competent authority
xxi. In case the site falls in the built-up area declared as slum under any Act NOC from the Competent Authority, from slum clearance and land use points of view.
xxii.In case the application is for a Farmhouse, Motel, approval/NOC from the Competent Authority from land acquisition point of view.
xxiii. In case of the leasehold plots, clearance from the lessor with regard to the lease conditions shall be obtained wherever required.
xxiv. For individual plot, wherever required, approval of the site from the Competent Authority, if not the part of already approved layout plan.
xxv. Site plan for all the authorities, and details as required by the approval authority
xxvi. Any other information/document, which the Authority may require in case of listed buildings or otherwise.
Other documents to be submitted in special cases shall be as follows:
i. For projects proposed within the Prohibited and Regulated areas as defined by AMASR Act 2010, permission /NOC from Competent Authority (NMA) shall have to be obtained as per Rules 2011 framed under the Act by submission of required documents as per rules.
ii. Additional documents required for conservation of Heritage sites including Heritage Buildings, Heritage/Precincts and Natural Features Areas (wherever required)
Note: The applicant shall submit all kinds of plans in electronic format of online portal of the competent authority. The competent authority shall convey objections/observations or sanction/refusal through online portal and or other prescribed mode.
(b)Every person applying under Code 4.1 shall appoint an architect/engineer for drawing up of building plans/structural drawings and for the supervision of erection or re-erection of the building.
(c)The supervision of erection or re-erection of residential or commercial buildings up to 9 meters height (G+2 floors including stilt floor) may be undertaken by the architect or the engineer. In case of buildings more than 9 meters in height, including stilt floor, the supervision shall be undertaken both by the architect and the engineer. In case of buildings in notified heritage zone, ecologicallyconservation zone, special protection zones, or as mentioned in Development Control Regulations and Master Plan, as well as for plots facing arterial, subarterial and collector roads, licensed architects need to approve designs, undertake feasibility study, and provide inputs regarding specific design interventions, and approval.
(d)During construction if appointed architect/engineer notices that violation(s), except compoundable, are continuing shall intimate the owner and advise him to stop further construction and rectify the violations and shall also intimate to the concernedauthority.
(e)The applicant, the architect and engineer shall digitally sign the application, plans, structural drawings, specifications, and the certificates as required in the relevant forms and documents, before making submission to the Competent Authority.
(f) In case the building application is returned, it may be re-submitted within Sixty (60) days from the date of such return without fresh scrutiny fee. Such re-submission, however, may not be allowed more than two times in Sixty (60) days from the date of first return.