(1) The owner who had applied under Code 4.1 and having building under Moderate Risk Category defined in Code 6.1(1), shall submit an application to the competent authority for grant of occupation certificate in Form BCS-III and along with completion drawings, Completion Certificate in Form BCS-IVA and along with the following documents:
(i) details of compoundable violations from the approved building plan (s), if any, in the building, jointly signed by the owner, architect and structural engineer, along with demand draft of the due payment for composition charges of such violations at the rates determined by the competent authority shall be submitted with Form BCS-III,
(ii) a certificate from third party (i.e., an architect or an engineer other than the architect/ engineer involved in designing, construction, and supervision of the building) in Form BCS-IVA that the building has been inspected in all respect and no provision of the Building Bye-Laws, has been violated excluding compoundable violations, and
(iii) photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc/ DVD containing all photographs shall also be submitted.
(2) The competent authority shall issue an occupation certificate in Form BCS-V within eight (8) working days of receipt of the Form BCS-III duly completed in all respects and accompanied with the required completion drawings, forms, and affidavits. The occupation certificate shall be issued provided that the documents submitted along with Form BCS-IVA are in order. Provided that if any violation (s) found within the time prescribed above during inspection, which is not listed in compoundable violations stated at Code 4.12 (1)(i), then the violation(s) be compounded or demolished by the competent authority if non-compoundable, as per composition charges prescribed.
(3) If no communication is received from the competent authority within eight (8) working days of submitting the application for “Occupation Certificate”, the owner is permitted to occupy building, considering deemed issuance of “Occupation certificate” and the application Form BCS-III shall act as “Occupation Certificate”. Provided that the violations, if found at any subsequent stage, shall result in cancellation of the occupation certificate issued and the
same shall be restored only after removal of violations. Further, action against the architect shall also be taken for furnishing a wrong certificate/affidavit.
(4) No person shall occupy or allow any other person to occupy any new building or a part thereof for any purpose whatsoever until such building or a part thereof has been certified by the competent authority as having been completed and an occupation certificate has been issued in his favour in Form BCS-V within the above-mentioned period.
(5) No occupation certificate shall be issued unless debris and rubbish consequent uponthe construction has been cleared from the site and its surroundings.
5.13 Revocation of Occupation Certificate
After the issuance of occupation certificate, if at any stage found that the building is used for some other purpose than as permitted to be used or made any addition/ alteration in the building then, after affording personal hearing to the owner, the competent authority may pass orders for revocation of occupation permission and the same shall be restored only after removal of violations.