The general requirement for inspection of the development shall also include the following regulation:
(A). General Requirements: The building unit intended to be developed shall be in conformity with Regulation on requirement of site. Generally all development work for which permission is required shall be subject to inspection by the Competent Authority as deemed fit.
The applicant shall keep a board at site of development mentioning the survey No, city survey No, Block No, Final Plot No., Sub plot No., etc. name of owner and name of Architect on Record, Engineer on Record , Developer, Structural Engineer on Record , Construction Engineer on Record.
(B). Record of Construction Progress
i) Stages for recording progress certificate and checking:-
a) Plinth, in case of basement before the casting of basement slab.
b) First storey.
c) Middle storey in case of High-rise building.
d) Last storey.
ii) At each of the above stages, the owner / developer / Builder shall submit to the designated officer of the Competent Authority a progress certificate in the given formats (Form No. 7-10). This progress certificate shall be signed by the Construction Engineer on Record.
iii) The progress certificate shall not be necessary in the following cases:
a) Alteration in Building not involving the structural part of the building.
b) Extension of existing residential building on the ground floor upto maximum 15 sq mt. in area.
iv) Completion Report
a) It shall be incumbent on every applicant whose plans have been approved, to submit a completion report in Form No.11.
b) It shall also be incumbent on every person / agency who is engaged under this Development Control Regulations to supervise the erection or reerection of the building, to submit the completion report in Form No.12, 13 and 14 prescribed under these Development Control Regulations.
c) No completion report shall be accepted unless completion plan is approved by the Competent Authority.
v) The final inspection of the work shall be made by the concerned Competent Authority within 21 days from the date of receipt of notice of completion report.
(C). Issue of Occupancy Certificate: The Authority issuing occupancy certificate before doing so shall ensure that following are complied with from consideration of safety against natural hazard.
i) Certificate of Lift Inspector has been procured & submitted by the owner, regarding satisfactory erection of Lift.
ii) The Certificate of Competent Authority and or fire department for completion and or fire requirements as provided in these regulations has been procured and submitted by the owner.
iii) If any project consists of more than one detached or semi detached building / buildings in a building unit and any building / buildings thereof is completed as per provisions of D.C.R. (Such as Parking, Common Plots, Internal Roads, Height of the Building, Infrastructure facilities, lift and fire safety measures), the competent authority may issue completion certificate for such one detached or semi detached building / buildings in a building unit.
The occupancy certificate shall not be issued unless the information is supplied by the Owner and the Architect on Record/ Engineer on Record concerned in the schedule as prescribed by the Competent Authority from time to time.