Fees and Charges for Grant of a Development Permission / Revised Development Permission / Revalidation of Development Permission
(Refer Rule No. 4.10.2, 4.11.2, 4.12.2, 4.13.2, 4.14.2, 4.15.2, 5.3, 5.4.1, 6.6.2)
A person applying for a Development Permission / Revised Development Permission / Revalidation of Permission shall have to pay the following Fees and Charges along with the application to the Competent Authority at the following rates:
A Fees:
1 Scrutiny Fees for Buildings:
The fees shall be paid for both – Direct Development Permission and Development Permission. The scrutiny fees shall be levied at the time of making an application for Development Permission.
Table No. S5A – 1: Scrutiny Fees for Building
| No | Type of Use | Rate per sq m of Built-Up Area (Subject to minimum fees of Rs. 1000/-) | |
| Building upto 15m height | Building more than 15m height | ||
| 1 | Residential | Rs. 5.00 | Rs. 10.00 |
| 2 | Commercial | Rs. 8.00 | Rs. 13.00 |
| 3 | Residential Cum Commercial | Rs. 6.00 | Rs. 11.00 |
| 4 | Industrial | Rs. 7.00 | Rs. 12.00 |
| 5 | Public Offices, Utilities | Rs. 4.00 | Rs. 9.00 |
| 6 | Others | Rs. 5.00 | Rs. 10.00 |
(*others: includes Health, Education, etc. and other than the above-mentioned type of land use)
• In case of a revised development permission, these shall be paid again.
In case of revalidation of lapsed / suspended development permission, these shall not be paid again, only a revalidation fee will be paid which will be 25% of the Scrutiny Fee already paid.
In case of cancellation of development permission, these shall be forfeited.
2 Fees for Subdivision / Amalgamation / Layout of Land
A One-time payment shall be made for approval of subdivision / amalgamation / layout of land. It shall be valid for a period of 5 years.
Table No. S5A – 2: Fees for Subdivision /Amalgamation / Layout of Building Unit / Plot
| No | Type of land Use | Rate per sq m of land (Subject to minimum fees of Rs. 1000/-) | |
| Amalgamation | Subdivision / Layout of Building Unit / Plot | ||
| 1 | Residential | Rs. 3.00 | Rs. 6.00 |
| 2 | Commercial | Rs. 4.00 | Rs. 8.00 |
| 3 | Residential Cum Commercial | Rs. 3.50 | Rs. 7.00 |
| 4 | Industrial | Rs. 5.00 | Rs. 10.00 |
| 5 | Public Offices, Utilities | Rs. 3.00 | Rs. 6.00 |
| 6 | Others | Rs. 4.00 | Rs. 8.00 |
(*others: includes Health, Education, etc. and other than the above-mentioned type of land use)
Page No 186
In case of a revised development permission, these shall be paid again.
In case of revalidation of lapsed / suspended development permission, these shall not be paid again, only a revalidation fee will be paid which will be 25% of the Scrutiny Fee already paid.
In case of cancellation of development permission, it shall be forfeited.
3 Fees for Mining, Quarrying and Brick Kiln Operations
Mining, quarrying and brick kiln with or without chimney and processing of lime, sagol etc. without construction‐ Rs.1,00,000 per 0.1 hectare or part thereof.
• In case of a revised development permission, these shall be paid again.
In case of revalidation of lapsed / suspended development permission, these shall not be paid again, only a revalidation fee will be paid which will be 25% of the Scrutiny Fee already paid.
In case of cancellation of development permission, it shall be forfeited.
B Charges
1 Charges for Change in Land Use:
Charges for change in land use shall be paid every time there is a change of use of land.
Page No 187
Table No. S5A – 3: Charges for Change of Land Use
| No | Type of land Use | Rate per sq m of land (Subject to minimum fees of Rs. 1000/-) |
|---|---|---|
| 1 | Residential | Rs. 25.00 |
| 2 | Commercial | Rs. 40.00 |
| 3 | Residential Cum Commercial | Rs. 40.00 |
| 4 | Industrial | Rs. 50.00 |
| 5 | Public Offices, Utilities | Rs. 10.00 |
| 6 | Others | Rs. 40.00 |
(*others: includes Health, Education, etc. and other than the above-mentioned type of land use)
2 Development Charges for Infrastructure:
The Development Charges for infrastructure shall be paid for both – Direct Development Permission and Development Permission.
The development charges for infrastructure shall be levied at the time of making an application for Development Permission.
Table No. S5A – 4: Development Charges for Buildings
| No | Type of land Use | Rate per sq m of Built up (Subject to minimum fees of Rs. 1000/-) |
|---|---|---|
| 1 | Residential | Rs. 50.00 |
| 2 | Commercial | Rs. 80.00 |
| 3 | Residential Cum Commercial | Rs. 80.00 |
| 4 | Industrial | Rs. 100.00 |
| 5 | Public Offices, Utilities | Rs. 20.00 |
| 6 | Others | Rs. 80.00 |
(*others: includes Health, Education, etc. and other than the above-mentioned type of land use)
• In case of a revision of development permission, the differential shall be paid.
• In case of revalidation of lapsed / suspended development permission, these shall not be paid again.
In case of cancellation of development permission, it shall be forfeited.
3 Stacking Charges
Stacking Charges shall be levied during grant of commencement certificate and charges will be taken per week.
Table No. S5A – 5: Charges for Stacking Building Material on Public Roads
C Other Charges/Fees
Other Charges / Fees shall be levied under the provisions of other Act and or instructed by Government.
Note: All Charges and Fees may be revised by MS PDA from time to time.
Page No 188
Schedule No. 5B
Fees and Charges for Grant of Occupancy Certificate / Change of Occupancy Certificate
(Refer Rule No. 6.5.2)
A Occupancy Certificate
A person applying for an Occupancy Certificate shall have to pay Fees along with the application to the Competent Authority at the following rates:
Table No. S5B – 1: Fees for Occupancy Certificate
| No. | Description | Fees equal to |
|---|---|---|
| (1) | (2) | (3) |
| 1 | If the Occupancy is in conformity with these Rules and no change from the permission granted. | 10% of the Development Permission Scrutiny Fees that is leviable on the building unit, as the case may be |
B Change of Occupancy
If the development use is in conformity with the General Development Rules but there is change of use, then a fee equal to two times of the Scrutiny Fees paid shall be paid. The Development Charges as per the new proposed use shall be paid – the earlier shall be forfeited.
Table No. S5B – 2: Fees for Change of Occupancy
| No. | Description | Fees equal to |
|---|---|---|
| (1) | (2) | (3) |
| 1 | In conformity with these Rules but with internal modification without any change in overall location and/or overall dimension or margins of the building. | Two times of the Development Permission Scrutiny Fees that is leviable on the building unit, as the case may be. |