1(a) No new building in the following categories in which there is a system of installation for supplying hot water shall be built unless the system of the installation is also having an auxiliary solar assisted water heating system:-
(a) Hospitals and Nursing Home.
(b) Hotels, Lodges, Guest Houses, Group Housing with a plot area of 4048 sq m.
(c) Hostels of Schools, Colleges and Training Centres with more than 100 Students.
(d) Barracks of armed forces, paramilitary forces and police.
(e) Individual residential buildings having plot area equal or more than 1 kanal (420 sq.mt).
(f) Functional Buildings of Railway Stations and Air Ports like waiting rooms, retiring rooms, rest rooms, inspection bungalows and catering units.
(g) Community Centres, Banquet Halls, Bhawans and buildings for similar use.
1(b) As regards to residential buildings, all houses on a site of one kanal will make provisions for solar water heating system having capacity of atleast 100 Ltr. and on a site of two kanals and above that of atleast 200 Ltr. The existing houses will provide these facilities within two years from the date these orders are notified in the official gazette.
II) Installation of Solar Water Heating System
(a) New Buildings: Clearance of plan for the construction of new buildings of the aforesaid categories shall only be given if they have a provision in the building design itself for an insulated pipeline from the rooftop in the building to various distribution points where hot water is required. The building must have a provision for continuous water supply to the solar water heating system. The building should also have open space on the rooftop, which receives direct sun light. The load bearing capacity of the roof should at least be 50 kg. per sq m. All new buildings of above said categories must complete installation of solar water heating systems before obtaining necessary license to commence their business.
(b) Existing Buildings: Installation of Solar Assisted Water Heating Systems in the existing building shall be made mandatory at the time, if allowed, to above said category provided there is a system or installation for supplying hot water.
(c) Capacity: The recommended minimum capacity shall not be less than 25 Ltr. per day for each bathroom and kitchen subject to the condition that maximum of50% of the total roof area is provided with the system.
(d) Specifications: Installation of Solar Assisted Water Heating Systems shall conform to BIS specification IS 12933. The solar collectors used in the system shall have the BIS certification mark.
III Installation of solar photo voltaic power plant
For installation of solar photo voltaic power plant refer Annexure - 2