2.1Notice for obtaining sanction of building plan:
Every person who intends to erect, re-erect or make additions/ alterations in any place in a building or demolish any building shall give notice to the sanctioning authority of his/her said intention in the prescribed CAF, which shall be accompanied by the following plans, statements and documents:
2.1.1 Plans and Drawings
a) Site Plan: Site plan, as per the details, specifications and signatures specified in bye-law 2.0.4, shall be submitted.
b) Layout Plan: For plots of area one hectare and above, layout plan/ revised layout plan prepared by the Architect/ Developer/Applicant shall be submitted. Layout Plan duly approved by the Competent Authority shall be submitted by the Architect/Developer/Applicant, along with building plan application, in case the authority to approve the layout plan is different from the authority to sanction the building plans. Layout plan submitted by the Architect/ Developer/Applicant shall be prepared and signed as per the details specified in bye-law 2.0.4.
c) Landscape Plan: Landscape plan shall be submitted for all proposals which require Delhi Urban Art Commission’s approval as per their guidelines. Landscape plans shall be prepared and signed as per the details specified in bye-law 2.0.4.
d) Service Plans: Service plans, prepared and signed as per the details specified in bye-law 2.0.4, shall be submitted.
e) Building Plans: Building plans, as per the details, specifications and signatures specified in bye-law 2.0.4, shall be submitted.
f) The Architect, while submitting building plan application, shall inspect the site and ensure that the building plans submitted are as per existing site conditions including existing construction, if any.
2.1.2 Ownership Documents
(a) Document(s) to establish the ownership of property such as Sale deed/ Lease deed/ Perpetual lease deed/ Conveyance deed/ Relinquishment deed/ Gift deed or any other legal documents.
(b) In case of leasehold property, lease deed along with extension of time for construction up to the date of application has to be submitted. In case lease deed has not been executed, NOC from the lessor has to be submitted.
(c) In case of Government Buildings, an undertaking from the Competent Authority of the concerned Government Department shall be sufficient.
2.1.3 Signing of CAF and Declarations:
CAF shall be signed by the owner, architect and other professionals, as applicable. The following declarations/ certificates shall be part of CAF:
Appointment of professionals such as architect, engineer, structural engineer, supervisor, landscape architect, town planner, etc., whichever are applicable along with valid registration/ qualification certificate of the professional(s). {Whenever there is a change in the appointed professional(s), an intimation to this effect shall be along with valid registration/ qualification certificate of the professional(s)}. The CAF shall also include Structural Safety Certificate, Certificate for Supervision-No Nuisance and Debris Removal, Indemnity for Basement.
Note: i) The requirement of submission of Notice of Commencement of Work to the concerned office/s of Sanctioning Authority has been done away with, in these Building bye-laws.
ii) Information on Tentative Date of Commencement and Completion should be provided while applying in CAF, and the same shall be forwarded Online to the Labour Department.
2.1.4 Soil Testing Report from Geo‐Technical Engineer
In case of high risk buildings, a Soil Testing Report from Geo‐Technical Engineer, having qualification and competence as per Annexure-I, shall be submitted. Structural drawings shall be prepared by taking this report into account.
Chapter 2Procedure and Documentation for Sanction/ Occupancy-cum-Completion of Building Plans
2.0 Overview of procedure and general requirement
2.0.1 Procedure
(a) For residential plots up to 105 sq.m in size forming a part of approved layout/ special areas/ unauthorized regularized colony/ village abadis/ lal dora /extended lal dora resettlement colonies and slum & JJ cluster/ Rehabilitation Colonies, excluding those within LBZ, the procedure and documentation shall be as per ‘SARAL’ scheme given in Chapter 4 of these Bye Laws.
(b) The entire process from applying for sanction of building plan to issue of occupancy-cum-completion certificate shall consist of following steps:
(i) Submission of application for sanction of building plan and NOC applications in Common Application Form (CAF) along with building permit fees, drawings and documents.
(ii) Grant of sanction within stipulated period, Payment of requisite fees & charges, as applicable, and release of sanctioned building plan.
(iii) Intimation of completion of work up to plinth level.
(iv) Plinth level inspection and online issue of plinth level inspection certificate.
(v) Submission of application for issue of Occupancy-cum-Completion Certificate (OCC) and NOCs (Fire, Water etc) in Common Occupancy-cum-Completion Certificate Request Form (COCCRF) along with requisite fees, drawings and documents.
(vi) Single joint site inspection by all concerned departments.
(vii) Intimation of compounding fee and charges, if applicable, and release of OCC along with completion plan.
(c) However, the above procedure shall stand amended to the extent specified in the fast track procedures specified in Chapter 3 based on risk-based classification of buildings.
(d) Building permit not required: No notice and building permit is required for addition/alterations which do not otherwise violate any provisions regarding building requirements, structural stability, fire safety requirements and involve no change to the cubic contents or to the built up area of the building, as defined in bye laws, for the following:
i. Plastering/ cladding and patch repairs *.
ii. Re-roofing or renewal of roof including roof of intermediate floor at the same height.
iii. Flooring and re- flooring.
iv. Opening and closing windows, ventilators and doors opening within the owner’s plot. No opening towards other’s property/ public property will be permitted.
v. Rehabilitation/repair of fallen bricks, stones, pillars, beams etc.
vi. Construction or reconstruction of sunshade not more than 75 cm in width within one’s own land and not overhanging over a public street;
vii. Construction or reconstruction of parapet and also construction or re-construction of boundary walls as permissible under these bye-laws;
viii. White washing, painting etc. including erection of false ceiling in any floor at the permissible clear height provided the false ceiling in no way can be put to use as a loft/ mezzanine, etc.
ix. Reconstruction of portions of buildings damaged by storm, rains, fire, earthquake or any other natural calamity to the same extent as existed prior to the damage as per sanctioned plan, provided the use conforms to provisions of MPD.
x. Erection or re-erection of internal partitions provided the same are within the preview of these bye-laws.
xi. For erection of lifts in existing buildings in residential plotted development (low–rise). Change/installation/ rearranging/ relocating of fixture(s) or equipment/s or HVAC-MEP services, UGR,STP/ETP without hindering other’s property/public property shall be permitted.
xii. Landscaping
xiii. Public art
xiv. Bank ATM (up to a maximum area of 9.0 sqm only), Public washroom, security room /guard room are permitted in setback area, provided it does not obstruct fire vehicles movement, in plot more than 3000 sqm (other than residential plotted), as per Chapter 12.
xv. Placing a porta cabin upto 4.5 sqm within the plot line subject to free fire tender movement.
Note: The liability for any structural flaws or defects in the buildings arising out of such additions/ alterations shall rest with the owner/ architect/ engineer/ structural engineer.
* For Heritage Buildings, refer Annexure II.
2.0.2 Information required from the applicant by the sanctioning authority and other agencies to be provided in CAF and COCCRF
(a) Information required from the applicant by the sanctioning authority and for granting No Objection Certificates by the internal/ external agencies such as Delhi Fire Services, Delhi Urban Art Commission, Airports Authority of India, Delhi Pollution Control Committee, Heritage Conservation Committee, Department of Forest, Department of Labour, Delhi Jal Board, National Monuments Authority, Chief Inspector of Factories, Director General of Explosives, etc., shall be provided in CAF/COCCRF, as applicable.
(b) Any undertaking/ declaration required by the sanctioning authority or any other agency, shall be part of CAF/COCCRF, as applicable.
2.0.3 Bulk characteristics for Development: Bulk characteristics for development on any specific plot can be determined by the owner/ concerned professional(s) by referring to the Master Plan for Delhi, Zonal Development Plan, layout plan, land records such as lease deed/ conveyance deed, allotment/ auction conditions, control drawings, other applicable guidelines, etc. The sanctioning authority shall ensure that the Master Plan for Delhi, Zonal Development Plans, approved layout plans, other applicable guidelines are made available free of cost in the public domain on their websites.
2.0.4 The plans/ drawings to be submitted at various stages of the process to the sanctioning authority shall adhere to the following requirements:
(a) Key Plan: Layout/ site plans shall include a key plan drawn to a scale of not less than 1:10,000 showing boundary and location of the site with respect to neighboring landmarks including North Point.
(b) Size of Drawing Sheets: Size of drawing sheets shall be any of those specified in table 2.1 below:
Table 2.1Standard Sizes of Drawings
S.No
Designation
Trimmed size, mm
1
A0
841x1189
2
A1
594x841
3
A2
420x594
4
A3
297x420
5
A4
210x297
6
A5
148x210
(c) All dimensions in drawings shall be indicated in metric unit.
(d) Recommended notation for colouring of plans: The site and building plans shall be coloured as specified in the table 2.2 given below. The colouring notation used for items, which are not listed in table 2.2, shall be indexed:
Table 2.2Colouring of Plans
S. No.
Item
Site Plan
Building Plan
1.
Plot lines
Thick green
Thick green
2.
Existing street
Green
Black Line
3.
Permissible building line
Thick dotted green
Black dash dot
4.
Existing work (Outline)
Green
Green
5.
Work proposed to be demolished
Yellow hatched
Yellow hatched
6
Proposed-- a) Additions/ Alterations. b) Entirely new work
Red Not to be coloured
Red Not to be coloured
7.
Drainage
Red dotted
Red dotted
8.
Water Supply
Blue dotted thin
Blue dotted thin
(e) Scales for Layout/ Site/ Landscape Plans:
(i) Layout plan prepared by the developer shall be in the scale of 1:10,000.
(ii) Site Plan shall be drawn to a scale as follows:
Site area
Scale (Preferable or readable scale)
Up to 1000 sqm
Not less than 1:200
More than 1000 sqm and up to 10,000 sqm
Not less than 1:500
(iii) Landscape Plan shall be readable, preferably on a scale of 1:500, indicating circulation, parking spaces, pathways, lawns, trees, shrubs, ground cover and climbers.
(f) Details to be shown in Site Plan
(i) The site should be a part of an approved layout plan. However, if there is no approved layout plan, the site will be governed by provisions of MPD/ ZDP. The site plan should be a detailed plan showing the proposed placement of structure/ building, parking area, open area, landscaping, and other development features as required by the specific sections of the Development Control Regulations of Master Plan for Delhi (MPD). The site plan shall also indicate boundaries, means of access, position of the site in relation to neighboring street(s), name(s) of these street(s), and width of the street in front of the site.
(ii) Further, the site plan shall show the direction of North point, existing physical features such as wells, drains, trees, etc., ground area of the site, the breakup of covered area (existing and proposed) on each floor (with the percentage of total plot area required under MPD governing the coverage of the area), number of floors, height, basement area, setback lines.
(g) Service Plans: Service plans shall include the following:
(i) Service plans for water supply, sewage disposal system and storm water disposal, wherever applicable, shall be as per the prescribed norms and standards of the sanctioning authority.
(ii) Service plans of building services such as plumbing, HVAC, installation of electrical fittings, etc., as per NBC norms and standards. are to be shown on the same scale as that of the building plan.
(h) Building Plans: The plans, elevations and sections of the buildings, shall be drawn to a readable scale or preferably to the scale of 1:50 for plots measuring up to 250 sqm. For plots measuring above 250 sqm to 500 sqm, these shall be drawn at the scale of 1:100. For plots measuring above 500 sqm, these shall be drawn at the scale of 1:200. If the drawings do not fit in the paper sizes listed in table 2.1, then suitable scale as per the proper size in the multiple of 100 can be adopted.
(i) Details to be shown on Plans: The plans shall include floor plans of all floors together with the covered area, clearly indicating the location and sizes of all components like rooms, staircases, ramps, exit ways, lift wells, etc. and indicating the use or occupancy of all parts of the building.
(ii) Details to be shown in Sections: The sections shall indicate the total height of buildings, rooms and the height of the parapet. At least one section should be taken through the staircase, kitchen, toilet, bath and W.C. and lift.
(iii) Details to be shown for all Elevations: Façade with total height of buildings, permissible projections beyond the permissible building line, location of doors, windows and other openings including ventilators with size in a schedule form.
(i) Signing of Plans
(i) Signing of Building plans: The building plans/drawings shall be digitally signed by the owner(s), the structural engineer and one of the following professionals, as per their competence indicated against them:
a. Architect (in case of any plot size)
b. Engineer (in case of plots up to 500 sq. m)
c. Supervisor (in case of plot up to 200sqm)
Note: Qualification and Competence of various professionals shall be as per Annexure-I.
(ii) Signing of Layout/ Site Plans: All Layout/ Site Plans shall be signed by the owner(s) and one of the following professionals, as per their competence indicated against them:
a. Town Planner (in case of any plot size)
b. Architect (in case of plots up to one hectare in size)
Note: Qualification and Competence of various professionals shall be as per Annexure-I.
(iii) Signing of Landscape Plan: Landscape Plan shall be signed by the owner(s) and one of the following professionals, as per their competence indicated against them:
a. Landscape Architect (in case of any plot size)
b. Architect (in case of plots up to two hectare in size)
Note: Qualification and Competence of various professionals shall be as per Annexure-I.
(iv) Signing of Service Plans: Service Plans shall be signed by the owner(s) and one of the following professionals:
a. Engineer for Utility Services; or
b. Architect
Note: Qualification and Competence of various professionals shall be as per Annexure-I.
(j) Requirement of Site
(i) Damp Site: Wherever the dampness of a site or the nature of the soil renders such precautions necessary, the ground surface of the site between the walls of any building erected thereon shall be rendered damp-proof to the satisfaction of the sanctioning authority.
(ii) Corner Site: Where the site abuts two streets, the frontage would be on the street having the larger width. In cases, where the two streets are of same width, then the larger depth of the site will decide the frontage and open spaces. In such case the location of a garage (on a corner plot) if provided within the open spaces shall be located diagonally opposite the point of intersection. However, the details of the frontage of the building should be as per the approved layout plan.
(iii) Minimum Size of Site: The minimum size of sites for the construction of different types of building or different use groups shall be mainly in accordance with provisions of the MPD and any land development Rules and Regulations of the sanctioning authority.
(iv) Means of Access: Every building/ plot shall abut on a public/ private means of access like streets/roads duly formed. In case of approved layout plan, the means of access shall be in accordance with provision of MPD.
(v) Distance from Electric Lines: No verandah, balcony, or the like shall be allowed to be erected or any additions or alterations made to a building within the space between the building and overhead electric supply line in accordance
with the Indian Electricity Rules (National Electric Code 2011, Clause 3.2) and its amendments from time to time The distances provided in NBC (Part III) are indicated in the table below:
Vertically (m)
Horizontally (m)
a) Low and medium voltage lines and service lines.
2.5
1.2
b)High voltage lines up to and including 11 KV
3.7
1.2
c)High voltage lines above 11 KV to and including 33KV
3.7
2.0
d) Extra high voltage lines beyond 33KV.
3.7(add 0.3 m for every extra 33KV or part thereof)
2.0(add 0.3 m for every extra 33KVor part thereof).
(k) Buildings shall be designed as per provisions specified in Chapters 7 to 13 of these bye-laws.
2.0.5 All communications/ intimations between owner/ applicant, sanctioning authority and any other statutory body shall be done by electronic means which includes online forms provided for such purpose, e-mails, information updated on online portals, etc.