7B Systems Building and Mixed/Composite Construction
3.1.1 Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code shall be referred for requirements of materials and also for the characteristics to be considered in their selection.
3.1.2 The materials used in prefabricated components may be many and the modern trend is to use concrete, ferrocement, steel, treated timber, aluminium, cellular concrete, light weight concrete, ceramic products, etc. However, this Subsection pertains to mixed/composite construction.
This shall be in accordance with Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code.
The formwork systems which are utilized in buildings shall be as given in 6.1 to 6.5.
This is a system which casts walls and slab monolithically in a single pour of concrete. Façade walls are precast or of block masonry to enable removal of tunnel form. All components of the formwork are made up of steel. This produces very rapid construction in a building where the plans are of modular nature suitable for this technology. Accelerated curing, if required, is possible enabling early stripping of formwork.
Slipform is a continuously moving form at such a speed that the concrete when exposed has already achieved enough strength to support the vertical pressure from concrete still in the form as well as to withstand nominal lateral forces. Slipform may be classified as straight slipform, tapering slipform and slipform for special applications. Construction of lift cores and stairwell using slipform technique comes under special applications because of their complex sizes, shapes and loads to be lifted along with the slipform like walkway truss, etc, which is essential for construction. This system uses hydraulic jacks avoiding crane for lifting of assembly during construction operation. This system facilitates rapid construction and continual casting, creating a monolithic structure thereby avoiding construction joints.
This system of formwork uses modular aluminium panels, which are light and rust free, in both sheathing and framework. It may be used for a broad range of applications from wall to slab construction panels to more complicated structures involving bay windows, stairs and hoods. Every component is light enough to be handled easily thereby minimizing the need for heavy lifting equipment.
This is a system, which gives an advantage of combining speed and quality of construction. The vertical load
carrying members are made of steel whereas the horizontal members are of plywood inserted into two wooden beams thereby forming a web flange. All the formwork and support systems shall be designed for the loads coming during the actual execution stage.
Any other/new system may be used for systems building after due examination and approval by the Authority.
For the purpose of this Subsection, the following definitions shall apply.
2.1 Authority Having Jurisdiction — The authority which has been created by a statute and which, for the purpose of administering the Code/Part, may authorize a committee or an official or an agency to act on its behalf; hereinafter called the ‘Authority’.
2.2 Basic Module — The fundamental module used in modular coordination, the size of which is selected for general application to building and its components.
NOTE — The value of the basic module has been chosen as 100 mm for the maximum flexibility and convenience. The symbol for the basic module is M.
2.3 Cellular Concrete — The material consisting of an inorganic binder (such as lime or cement or both) in combination with a finely ground material containing siliceous acid (such as sand), gas generating material (for example, aluminium powder), water and harmless additives (optional); and steam cured under pressure in autoclaves.
2.4 Component — A building product formed as a distinct unit having specified sizes in three dimensions.
2.5 Composite/Mixed Construction — Construction involving two or more different kinds of components such as prefabricated structural units of steel, prestressed concrete or reinforced concrete and cast in-situ concrete, ferrocement, timber, masonry in brickwork and blockwork, glass and glazing connected together in such a manner that they act integrally.
2.6 Increments — Difference between two homologous dimensions of components of successive sizes.
2.7 Module — A unit of size used in dimensional coordination.
2.8 Modular Coordination — Dimensional coordination employing the basic module or a multimodule.
NOTE — The purposes of modular coordination are:
a) To reduce the variety of component sizes produced, and
b) To allow the building designer greater flexibility in the arrangement of components.
2.9 Modular Grid — A rectangular coordinate reference system in which the distance between consecutive lines is the basic module or a multimodule. This multimodule may differ for each of the three orthogonal dimensions of the grid, two in plan and one in vertical direction.
2.10 Multimodule — A module whose size is a selected multiple of the basic module.
2.11 Prefabricate — Fabrication of components or assembled units prior to erection or installation in a building.
2.12 Prefabricated Building — The partly/fully assembled and erected building, of which the structural parts consist of prefabricated individual units or assemblies using ordinary or controlled materials, including service facilities; and in which the service equipment may be either prefabricated or constructed in-situ.
2.13 Sandwich Panels — Panels made by sandwiching a layer of insulation material between two outer layers of hard durable materials like steel, dense concrete, plastic, cement based sheet, ceramic, etc. The hard coverings on two outer faces may be of same or different materials; the three layers may or may not be bonded with each other to behave as a composite panel.
2.14 Self-Compacting Concrete — Concrete that is able to flow under its own weight and completely fill the voids with in the formwork, even in the presence of dense reinforcement without any vibration, whilst maintaining homogeneity without segregation.
2.15 Shear Connectors — Structural elements, such as anchors, studs, channels, loops and spirals, intended to transmit the shear between the prefabricated member
and the cast in-situ concrete and also to prevent separation at the interface.
2.16 System — The method of construction of buildings with certain order and discipline and repetitive operations using the prefabricated components, tunnel form or engineered shuttering, where the work is organized and follows a defined procedure.
2.17 Unit — Building material formed as a simple article with all three dimensions specified, complete in itself but intended to be part of a compound unit or complete building. Examples are brick, block, tile, etc.
This shall be in accordance with Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code.
This shall be in accordance with Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code.
5.1 The preferred dimensions of precast elements used and their casting tolerances shall be in accordance with
Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code.
5.2 The permissible tolerances of timber used shall be in accordance Part 6 ‘Structural Design, Section 3 Timber and Bamboo, Subsection 3A Timber’ of the Code.
5.3 For permissible tolerances of steel and masonry, reference may be made to relevant Indian Standards.
7.1 Several schemes are possible, with certain constraints, using the same set of components. The degree of flexibility varies from system to system. However, in all the systems there is a certain order and discipline.
7.2 The following aspects, among others, are to be considered in devising a system:
a) Effective utilization of spaces;
b) Straight and simple walling scheme;
c) Limited sizes and numbers of components;
d) Limited opening in bearing walls;
e) Regulated locations of partitions;
f) Standardized service and stair units;
g) Limited sizes of doors and windows with regulated positions;
h) Structural clarity and efficiency;
j) Suitability for adoption in low and high rise building;
k) Ease of manufacturing, storing and transporting;
m) Speed and ease of erection;
n) Optimization of available handling equipment; and
p) Simple jointing system.
The system of mixed/composite construction depends on the extent of the use of prefabricated components, their materials, sizes and the technique adopted for their manufacture and use in building.
The following combinations may be used in mixed/ composite construction:
a) Structural steel work and timber roofs on precast frames.
b) Precast floors onto steel and concrete beams, and masonry walls.
c) Profiled metal decking on precast beams.
d) Precast frames onto cast in-situ foundations, retaining walls, etc.
e) Precast frames stabilized by masonry walls, steel bracing, etc.
f) Precast cladding in steel or cast in-situ frames and vice-versa.
g) Glass curtain walling (see Part 6 ‘Structural Design, Section 8 Glass and Glazing’ of the Code), stone cladding or metal sheeting onto precast concrete frames, etc.
h) Reinforced concrete and structural steel as composite columns and beams.
7.3.1.1 Precast concrete may be combined with cast in-situ concrete, often termed hybrid construction. Cast in-situ is mostly used to form homogenous connections between precast elements and provide a structural topping for horizontal diaphragm action. In other cases it is used to form the foundations and sub-structure to the building.
7.3.1.2 Structural steel work is largely used in long span prestressed concrete floors supported on rolled and prefabricated steel beams and also as steel roof trusses supported on concrete columns.
7.3.1.3 Timber may be used as long span glue-laminated beams and rafters, with precast concrete. Precast floors may be used in timber frame construction. Similarly, timber frames with precast elements shall be used as a building system.
7.3.1.4 Brick and block masonry may be combined with precast concrete structures and floors. The most common combinations is to use prestressed floors on load bearing walls.
8.1 The mixed/composite structures shall be analyzed appropriately and the joints in them designed to take the forces of an equivalent discrete system. Resistance to horizontal loading shall be provided by placing beams, walls and/or bracings in two directions at right angles or otherwise. The individual components shall be designed, taking into consideration appropriate end conditions and loads at various stages of construction. The components of the structure shall be designed for loads in accordance with Part 6 'Structural Design, Section 1 Loads, Forces and Effects' of the Code. In addition, members shall be designed for handling, erection and impact loads that may be expected during handling and erection.
8.2 For mixed and composite construction the following shall be considered:
a) Positions of stability cores, walls, bracing, etc — In high rise buildings, the most
popular method is a central core constructed several storeys ahead of the framework. The core could be built using precast concrete panels, CIP walls, steel cross bracing or precast concrete diagonal bracing.
b) Maturity of connections — Cast in-situ grouted joints need temporary propping until desired design strength is achieved unless combined mechanical connections are also used. The overall construction sequence should be planned ahead of time carefully as per the design requirements. The design of temporary bracing system using key components should be looked at critically.
c) The availability and/or positioning of equipments to transport and erect components — The size and weight of the various components shall be organized to make optimum use of crane capacity, for example, the lightest units farthest from the operating zone.
d) Erection safety and speed of construction, with attention to cast in-situ concreting sequences — This is particularly important where fixing gangs are unaccustomed to working with different materials.
e) Tolerances for economical construction — This is particularly important where different manufacturers are producing components in different materials.
8.3 Other design considerations and safety requirements against progressive collapse shall be in accordance with Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code.
The requirements relating to manufacture, storage, transport and erection of precast concrete elements shall be in accordance with Part 6 ‘Structural Design, Section 7 Prefabrication, Systems Building and Mixed/Composite Construction, Subsection 7A Prefabricated Concrete’ of the Code, including the requirements applicable to mixed/composite constructions given therein.
Constructional practices relating to decking shall be as given in Annex A.
Concreting on decking shall be carried out in accordance with Annex B.