Ranjangaon Growth Centre is envisioned to become an “Integrated Industrial Town” based on the following key considerations:
-
presence of well established MIDC estates abutting the Pune-Ahmednagar Highway
-
MIDC development and future expansion providing high employment opportunities
-
the need for good quality living ecosystem complementing the industrial use
-
increase in demand for the standard of living through the development of social infrastructure
-
appetite for real estate for affordable housing through townships and town planning scheme to arrest the daily to and fro commute from PMC/Wagholi
-
Ranjangaon Ganpati, a pilgrimage destination, need for state of the art facilities to enable the pilgrims and boost tourism activities
Understanding the above, three new nodes are proposed surrounding the MIDC estate, first at Ranjangaon Ganpati, then at Karegaon and Shirur Council with a balanced distribution of amenities and infrastructure. Also, the high demand for the electronics industry is anticipated with future urbanisation and digitisation of the economy, proposed at Karegaon as an extension to existing industrial activities. Thus the development of SMEs as part of the electronic segment would be the economic focus of the area that would leverage the “Integrated Industrial Town”.
| Villages | 2011 | 2018 | 2031 | 2041 |
|---|---|---|---|---|
| Dhok Sangavi | 2987 | 4139 | 7,061 | 10,065 |
| Karegaon | 5257 | 10207 | 13,817 | 17,193 |
| Ranjangaon Ganpati | 13427 | 23632 | 41,743 | 60,791 |
| Shirur (Annapur, Saradwadi, Tardobachiwadi, Kardilwadi) | 18710 | 49466 | 60,738 | 71,455 |
| Total | 40381 | 84444 | 123,359 | 159,504 |
The projected resident workforce based on the projected population through the URGD method is 50,045. Considering the proposed economic activities of all the growth centres, employment distribution was proposed based on the envisaged sectoral split for that Growth Centres. Accordingly, the employment to be generated for the Growth Centre for the year 2041 is estimated to be 93,455. The proposed residential density is about 125 PPH (12,500 persons/sq km).
For the planning of public facilities distribution, the Ranjangaon Growth Center is divided into two sectors; one is east of the Growth Centre consisting of Shirur Part, and the other is to the west consisting of Karegaon, Dhok Sangavi and Ranjangaon Ganpati. The boundaries of this planning division are shown on the Proposed Zoning Map. The projected sector-wise population statement is in Table 35.4.
| Sector | 2011 | 2018 | 2031 | 2041 |
|---|---|---|---|---|
| Sector 1 | 21,671 | 37978 | 62,621 | 88,195 |
| Sector 2 | 18,710 | 49466 | 60,738 | 71,455 |
| Total | 40,381 | 87444 | 1,23,359 | 1,59,650 |
The proposed zoning would guide and determine the optimal and efficient land use for the next 20 years. The proposed zoning plan is an output of existing land use and physical conditions analysis, understanding of most pressing issues of the Growth Center, local knowledge of the place and deployment of five planning goals and allied physical planning strategies. The proposed zoning area statement is presented in Table 35.5.
Figure 35.4: Proposed Zoning Map

Chapter 35: Growth Centre: Ranjangaon
| Land use category | Area (ha) | Proportion of Total Devel-oped Area (%) | Proportion of Total Area (%) |
|---|---|---|---|
| Residential | 1731.09 | 40.79 | 22.95 |
| Gaothan | 27.44 | 0.65 | 0.36 |
| Commercial | 127.76 | 3.01 | 1.69 |
| Industrial | 810.16 | 19.09 | 10.74 |
| Public and semi public | 35.40 | 0.83 | 0.47 |
| Public Utility | 10.53 | 0.25 | 0.14 |
| Traffic & Transportation | 459.89 | 10.84 | 6.10 |
| MIDC | 1041.50 | 24.54 | 13.81 |
| Total Developed Area | 4243.7 | 56.27 | |
| Agriculture (G1) | 2616.84 | 34.70 | |
| Water bodies | 164.16 | 2.18 | |
| Green Belt | 86.97 | 1.15 | |
| Forest | 96.06 | 1.27 | |
| Hilltop Hillslope | 274.21 | 3.64 | |
| Recreational | 37.04 | 0.49 | |
| Quarry | 22.41 | 0.30 | |
| Total Non-Developable Area | 3297.68 | 43.73 | |
| Total | 7541.46 | 100.00 |
Proposed zoning ensures that the sectoral development goals are clearly conveyed through it. Proposed sectoral goals and their corresponding physical planning strategies are mentioned in Table 35.6.
| Goals | Development Sector Addressed | Physical Planning Strategies |
|---|---|---|
| Prudent | Employment and housing | Work- Live Hubs |
| Convenient | Roads and mass transport | Movement Lattice |
| Resilient | Environment protection | Green- Blue connectors |
| Efficient | Infrastructure and utilities | Decentralized resource management |
| Self- sufficient | Social facilities | Walkable Neighbourhoods |
For Ranjangaon Growth Center, the Work-Live concept is applied by:
-
Designating residential zones within 500 m around industrial and commercial zones to minimize workrelated trips for at least 30% of the resident workforce
-
Allocating new industrial and commercial zones along the Pune-Ahmednagar Highway edging the MIDC area, equidistance from Ranjangaon and Shirur to reduce travel time for commuting workforce from within and other Growth Centers
-
Proposing Town centre at Karegaon, at a central location of the Growth Centre
Out of the total proposed industrial zone over 186.6 sq km, industrial use over 18.51 sq km is envisaged in Ranjangaon Growth Centre, both based on projected employment and 50 workers/ha density, which includes 10.41 sq. km of MIDC development.
The industrial zone as per ELU was 0.51sq km (outside MIDC). Considering the existing MIDC development and spotted small scale ancillary industrial development scenario, within the Growth Centre and the planning intent, 18.5 sq km of the industrial zone is proposed in Ranjangaon Growth Centre.
The planning intent is to allow expansion for industries edging the MIDC estate to synergies the probable electronic and ancillary SMEs supporting the MIDC industries as part of the industrial ecosystem. It is also connected to rural catchments utilizing MDRs and village roads to support the agriculture sector.
Land requirement for the residential zone is estimated based on a net residential density of 125 PPH. Further, 45% add-on is considered to account for amenity (15%), open spaces (10%) and roads (20%). Accordingly, the total gross area required for the projected GC population of 1,59,504 by 2041 is estimated to be 18.5 sq km.
Considering the projected population, net residential density, proposed role and existing growth trends within the Growth Centre, 17.43 sq km of gross residential zone is proposed. Understanding the existing mature settlements in Ranjangaon Ganpati and south of Shirur Municipal Council, these residential nodes are expanded to accommodate their future population. With the above mentioned projected higher density, around 435 ha is proposed near Ranjangaon while 643 ha is proposed in the south of Shirur Municipal Council. A new residential node with 120 ha of the area is introduced at Karegaon, aligning the Pune-Ahmednagar Highway catering to the MIDC development. Only 38 ha are proposed around the Dhok Sangavi as part of the Gaothan expansion boundary of 200 m. EWS housing is proposed at Karegaon to facilitate affordable housing projects.
Three commercial nodes are proposed, namely at Ranjangaon Ganpati, Karegaon and Shirur Part. Warehousing and logistic activities are observed at Karegaon. Thus a commercial zone is proposed supporting the service industry activities complementing industrial development. In contrast, the commercial zone proposed at Ranjangaon Ganpati is with an intention to leverage the hospitality sector supporting tourist activities near the Maha-Ganapati temple precinct. Land requirement for the commercial zone is estimated based on URDPFI guidelines, i.e. 0.6 ha per 1,000 population Add on of 30% is considered to account for roads (15%), open spaces (10%) and amenities (5%). Accordingly, the total commercial zone requirement for the Study Area is estimated to be 23.77 sq km. 1.27 sq km from this area is proposed in the Growth Centre such that equitable distribution of commercial activities is facilitated.
‘Convenient’ goal would be addressed by developing a robust road network so that all the developable areas would be conveniently accessible. It implies a lattice (a grid) formed by the existing/proposed roads following a maximum spacing of 300 m - 500 m. This would ensure that road density in the Growth Center would increase (> 1km/sq km) to make it accessible and to improve its carrying capacity.
The movement lattice concept also includes a mass transit corridor running through the Growth Center centre,
Chapter 35: Growth Centre: Ranjangaon
high-speed rail crossing the Centre and Ring Road to encourage >50% of the residents to use mass transport for their daily commute.
-
A parallel system (30 m road) is proposed to NH-753F on its southern side, bypassing the congested section along the MIDC estate and disconnecting it from local traffic, starting from Ranjangaon until Shirur.
-
24m bypass is proposed to NH-753 F at Shirur village
-
A radial grid of collector roads (24-15 m wide) is proposed at Ranjangaon Ganpati and Karegaon.
-
Collector roads (15-24 m wide) follow spacing of 300-500 m, while Secondary arterial (30-45 m wide) follows a grid of 1 to 2 km.
-
Secondary arterials have the flexibility to run a dedicated bus service for faster transport and support the feeder system and last-mile connectivity.
-
All existing roads to be redeveloped and proposed roads are to be designated with at least 3m wide footpath on either side of the road, as the ‘pedestrian right of way’ and as ‘hawker-free zone.’
Figure 35.5: Proposed Transport Network Map

| Road Category | Road names/ ROWs | Proposed ROWs | Authorit | y Total Length (km) Cveolsotp omfe Rnota (dCr D.)e- |
|---|---|---|---|---|
| Primary | NH753F | 60 | NHAI | 19.75 |
| Secondary | SH103 | 45 | PWD | 9.86 |
| Tertiary | MDR114MDR115MDR19MDR52MDR100 | 2424242424 | PWD PWD PWD PWD PWD | 6.018.694.272.842.90 |
| ODR145 | 18 | ZP | 0.32 | ||
| ODR148 | 18 | ZP | 5.46 | ||
| Local | VR (Total) | 15 | ZP | 14.23 | |
| DP Roads | |||||
| Primary | MSRDC Ring Road | 110 | MSRDC | 0.00 | 0 |
| Expressway | 90 | MSRTC | 0.00 | 0 | |
| PMRDA Ring Road | 65 | PMRDA | 0.00 | 0 | |
| Secondary | 45 | PMRDA | 0.00 | 0 | |
| 30 | PMRDA | 12.90 | 221.15 | ||
| Tertiary | 24 | PMRDA | 10.51 | 373.99 | |
| 18 | PMRDA | 24.59 | 229.19 | ||
| 15 | PMRDA | 32.55 | 259.69 | ||
| Local | 12 | PMRDA | 7.79 | 52.05 | |
| Total Road Length | 162.67 | ||||
“Resilient” goal aims to strengthen the inbuilt capacity of Growth Centres to sustain in adverse climatic conditions such as flooding, landslide, air pollution and climate change by protecting environmental features and land susceptible to such threats. The goal also aims to make these features accessible for passive recreation to cover the existing deficit of recreational spaces. It translated into the plan employing the Green- Blue Connector Strategy. ‘Green’ refers to the protected forests and slopes; ‘Blue’ refers to the protected water bodies; and ‘Connector’ refers to the proposed avenues and streams/ canals. Avenue is conceived as a tree-lined road, with NMT provision, linking the Green and Blue features.
-
The existing forest at Dhok Sangavi and the forest edging the Ghod River is designated as a protected area.
-
Green Zone to be reserved between the river bank up to the blue line for Ghod River.
-
All existing streams to be protected.
-
ROW of Chas Kaman Left bank canal to be protected.
-
These protected Green-Blue features are recommended to be connected by a 30-45m wide secondary arterial road that would be upgraded as a tree-lined avenue by developing NMT corridors (>3 m each) on both sides of the road and segregated from footpaths.
-
Green lungs are proposed within 500 m walkable distance covering an area of 119.41 ha. These green lungs include active and passive recreational spaces. The total active recreational space works out to be 22.08 ha that include playgrounds, sport complex, stadium and multi-purpose ground. And the total passive recreational space works out to be 97.32 ha that include gardens, town park/ regional park, bio diversity park and green belt.
Chapter 35: Growth Centre: Ranjangaon
This concept is applied as follow:
-
A solid waste site is proposed at Dhok Sangvi village
-
2 Sewerage treatment plants are proposed, one at Ranjangaon along a stream and another at Shirur part along Ghod River.
-
The effluent treatment plant is proposed adjoining MIDC at Karegaon.
-
2 WTPs are proposed at higher elevation within Karegaon, having a central location and another at Dhok Sangavi.
-
ETP is proposed at Karegaon abutting a water stream along the NH-753F, treating industrial waste, especially from the MIDC area.
-
Renewable energy sites could be proposed and are recommended on higher elevations. However, they would be finalised after a detailed study
-
A 220 kV substation is present within Ranjangaon MIDC
-
Currently, six cremation grounds are present in the Growth Centre. Thus no new additions are proposed as it satisfies the requirement
-
Since there exists a fire station within MIDC, no new fire station is provided.
| Infrastructure Sys-tem | Demand (2041) | Unit | Utility Sites | Total Area |
|---|---|---|---|---|
| Water Supply | 11.56 | MMC | 02 WTP | 1.47 |
| Sewerage | 11.48 | MMC | 02 STP | 4.07 |
| Solid Waste | 47.85 | Tones/day | 01 SWM | 2.08 |
Self-sufficient: Walkable Neighbourhoods
This goal is set to increase the liability index of the Growth Centre. To do that, amenities are proposed within 500 m distance, leveraging the concept of Walkable Neighbourhoods. The concept entails providing basic infrastructure and services for education, health, sports, and recreation within the neighbourhood to have easy access to them by foot.
-
Amenity provision is made for the projected population by 2031(1,23,358)
-
Neighbourhood level amenities are located within a 500 m radius from residential zones and are connected by collector/local roads to improve their accessibility from other neighbourhoods.
Ranjangaon Ganpati is the only established urban centre in the Growth Centre. Thus the concentration of amenities is observed in Ranjangaon Ganpati.
Education: Existing schools are well serving the GC, and thus no new schools are proposed. Wherever possible, expansion to the existing ZP schools is proposed with proper road access to each amenity. One primary plus secondary school os proposed at Karegaon. No new college is proposed within the Growth Centre as Shree Mahaganpati Junior College exists at Ranjangaon, and Shri Sitabai Thite College is in Shirur, already serving the locality.
Health: HC is provided considering walking radius within a Neighbourhood. 3 health centres are proposed, each at Shirur, Karegaon and Dhok Sangavi while the hospital is provided at Karegaon, a central location and served by a national highway/secondary arterial.
Socio-Cultural: Community halls are provided considering walking radius distance within a Neighbourhood. 6 community halls are proposed at Karegaon(1), Shirur (2) and Ranjangaon (3). Socio-cultural centre (possibility of Yatri Niwas to be integrated) is provided at Ranjangaon Ganpati, abutting a Neighbourhood
Garden near the Maha-Ganapati Temple complex serving the pilgrims as recreational space and a tourist attraction.
Open Space: Playgrounds are located near existing schools and are split into 2 with a minimum area of 0.8 ha to improve spatial distribution wherever required. 16 playgrounds are proposed, Ranjangaon (6), Karegaon (3), Dhok Sangavi (1) and Shirur (6). Neighbourhood Garden, Town Parks are provided along/ near water bodies, within the green belt or on Government-owned Gairan lands. 11 neighbourhood gardens are proposed, 4 at SHirur, 4 at Ranjangaon, 2 at Karegon and 1 at Dhok Sangavi. The sports complex is provided at the newly opened up residential zone at Karegaon, within the proposed Town Planning Scheme. Town Park is provided along the Ghod River within the green belt in Shirur part.
Commercial: Shopping centre/market is provided at existing commercial nodes/near existing settlements/ available amenity spaces. 3 markets are proposed, 1 at Shirur (amenity space), at Karegaon over government land along NH-753 F and lastly at Ranjangaon Ganpati adjacent to the highway. Town Centre is provided at a central location at Karegaon.
Residential: Two public housing proposals are provided, one at Ranjangaon and other at Kargaon, over government owned land serving the adjoining industrial / commercial activities, covered under the PMAY scheme.
Transport: A bus stop is proposed at the junction of SH-113 and NH-753F, while a bus depot is proposed at Ranjangaon Ganpati over a government land along the NH-753F with a truck terminal opposite to it, adjoining proposed warehouse reservation. Parking places are proposed next to amenities that provide for a larger crowd congregation.
Civic facilities requested by various government authorities: In addition to the above amenities, a warehouse of 2 ha as requested by State Warehousing Corporation is proposed adjoining the MIDC development as part of the industrial ecosystem. A bus depot as requested by PMPML and a truck terminal as per CTTS requirement are proposed at Ranjangaon Ganpati in a clustered approach.
| Land Ownership | No of Amenity | Total Area (ha) |
|---|---|---|
| Government Land | 9 | 11.7 |
| Private Land | 45 | 60.36 |
| Amenity Space | 10 | 4.3 |
| Other | 1 | 1.14 |
| Total | 65 | 77.5 |
- Town Planning Scheme: PMRDA envisages implementing the Development Plan proposals by enabling the provision of Town Planning Schemes, which will considerably reduce liability towards the direct cost of acquisition of land required for social and physical infrastructure. To achieve the economic role of ‘Integrated Industrial Town’, a town planning scheme is proposed at Karegaon. The reservations developed by the TPS mechanism are as follows:
a. Amenities: Town centre, cultural centre, sports complex, market, playgrounds and garden
-
The other proposals/reservations of the Development Plan are proposed to be acquired and developed through the mechanism of Accommodation of Reservation and Transfer of Development Rights (TDR) policy. It is estimated that all proposed roads and 50% of the public reservations will be acquired through TDR/FSI/ AR. Remaining
-
The remaining reservations will be acquired under the provision of the Land Acquisition Act by paying monetary compensation.