3.17.1 Issuing completion certificate
(1) On completion of all works at site that have been certified by the empanelled professionals as specified in Appendix-XII, as per the specifications and other provisions of these Bye-laws, the principal professional on record for supervising the works(for supervising the major civil works), shall issue Completion Certificate in Form-XIII, endorsed by all other concerned professionals on record for supervising various
components of the building along with the certification of Structural design and safety in Form-XV.
(2) In case of independent residential houses and Industrial buildings, the Professional on record shall issue work completion certificate only if all the works within the building and the yard are completed and the same is certified by the empanelled professionals.
(3) In case of other residential and non-residential buildings, the Professional on record shall issue work completion certificate only if all the works are completed in the Model areas of the building, the exterior of the building and services to be provided in the apartments, commercial and other premises of the building are also completed and certified by the Empanelled professional.
Provided that, in case of partial completion of the building, partial work completion certificate may be issued by the professional on record for the number of floors (starting from the lowermost floor moving upwards) upto which all works of the Model areas and exterior of the building are completed and services to be provided in the apartments, commercial and other premises of those floors of the building are also completed.
3.17.2 Application for approval of works from other departments
(1) The professional on record for preparing drawings and details for all the applicable NOCs from other departments, for the project, shall submit the required applications in Form-II (any or all of a, b, c, d, e, f, g, h, i and j, as applicable), for approvals from other departments for the construction done at site as per the NOCs issued.
(2) On receiving the work Completion Certificate and the application to various departments for approving the works executed at sites as per the NOCs issued, the Authority shall intimate all the concerned departments which have issued NOCs, along with the certification done by the empanelled professional, for issuing the prescribed certificate of approval for the construction done at site, wherever applicable.
(3) On receiving the intimation from the Authority, the concerned departments which had issued NOCs, shall issue the required certificates of approval for the construction done at site, wherever applicable, with or without site inspection.
(4) During the site inspection, according to the designated officer of the concerned department, if any of the works executed at site is not as per the conditions/specifications of the NOC issued, he shall issue endorsement through the Authority, to the applicant, along with the photographs of the defective works, to rectify the defects.
(5) On receiving the endorsement from such departments through the Authority, the applicant shall rectify the defects and intimate the concerned department.
(6) According to the Applicant or the concerned professional on record for supervision of work (for which endorsement is received from the concerned department), if the defects mentioned in the endorsement is incorrect, the Applicant may file objection, to the concerned department and the Authority, stating the correctness of the works executed, along with the photos to prove the correctness, if required.
(7) If objection is received from the Applicant, the Commissioner of the Authority shall conduct joint inspection along with the Applicant, the concerned professional on record, the Empanelled professional who has certified the work and the designated officer of the concerned Department who has issued the endorsement for defective work, by giving notice to all, to conduct joint inspection within seven days of receiving objection.
(8) During the joint inspection, the Commissioner of the Authority, after hearing the views of both the parties, shall either accept or reject the objection raised by the applicant and instruct the Applicant accordingly after making his inspection report in Form-XII (copy of the same to be sent to the designated officer of the concerned department) and the decision of the Commissioner shall be final. The Applicant shall abide by the decision of the Authority and rectify the defects mentioned in Form-XII, if any and intimate the Authority.
(9) On receiving the intimation of defect rectification by the Applicant, the Authority shall inform the Empanelled professional to inspect and certify the rectified work.
(10) The Empanelled professional shall inspect the site and after checking the work rectified as indicated in Form- XII, certify the same in Form- X within three days of receiving intimation.
(11) The Authority shall forward the certification issued in Form-X by the empanelled professional, to the concerned department and the concerned shall issue the required certificate of approval for the construction done at site, with or without site inspection