8.6Discretionary Powers: - Temporary Constructions and Relaxation for Hardship
8.6.1 General: - In conformity with the intent and spirit of these provisions the Authority, after obtaining consent of the Chief Planner, M.I.D.C., may : -
(i) decide on matters where it is alleged that there is an error in any order, decision, determination or reading made by him in the application of these Provisions ;
(ii) determine and establish the location of zonal boundaries in exceptional cases, or in cases of doubt or controversy ;
(iii) construe the provisions of these provisions where the street layout actually on the ground varies from the street layout as shown in the Development Plans ;
(iv) modify the limit of a zone where the boundary line of the zone divides a plot ; and
(v) authorise the erection of building or use of premises for a public service undertaking for public utility purposes only, where he finds such an authorisation to be reasonably necessary for the public convenience and welfare even if it is not permitted in any Land Use Classification.
8.6.2 Relaxation for Hardship : - In specific cases, where a clearly demonstrable hardship is caused, the Authority, after obtaining consent of the Chief Planner M.I.D.C., may, by a special written permission and after payment of premium, permit any of the dimensions / provisions prescribed by these Clauses to be modified, provided the relaxation sought for does not violate the health safety, fire safety, structural safety and public safety of the inhabitants of the buildings and the neighbourhood. However, no relaxation from the setback required from the road boundary or in parking requirements shall be granted under any circumstances. While granting permission under this Clause, conditions may be
(.f.y.)---4
38 ER T, - a , T , 3 3-,R0/ R-, T 3
imposed on size, cost or duration of the structure, abrogation of claim of compensation, payment of deposit and its forfeiture for non-compliance.
8.6.3 Temporary Constructions : - The Authority may grant permission for temporary construction for a period not exceeding six months at a time and one year in the aggregate for the construction of the following, viz .:-
i. Structures for protection from rain or for covering of the terraces during monsoon season only.
ii. Pandals for fairs, ceremonies, religious functions, etc.
iii. Godowns for storage of construction materials within the site during the period of construction.
iv. Site offices and watchman cabins within the site and only during the phase of construction.
v. Structures for exhibitions/ circuses, sale of crackers, seasonal goods etc. subject to approval of the Chief Fire Officer of Special Planning Authority.
vi. Within a site for a factory, structures for storage of machinery before its installation during the period of construction..
vii. Structures for ancillary activities of quarrying operations in conforming zones.
viii. MAFCO stalls, government milk booths and telephone booths.
ix. Transit accommodation for persons to be rehabilitated in a new construction.
x. Structures for labour camp and educational and medical facilities for the labour camp within the site of the proposed building during the phase of planning and construction of the proposed building.
xi. Asphalt Mixing / RMC (Ready Mix Concrete) plant in industrial zone during the period of construction..
xii. Stone quarrying and metal crushing units during the period of construction.
Provided that, items may be added to or deleted from the above list of temporary constructions with the consent of the Chief Planner of M.I.D.C.
Provided further that, temporary constructions for structures etc. mentioned at (iii), (iv), (vi), (ix) to (xii) may be permitted to be continued temporarily by the Authority, but in any case not beyond completion of construction and that structure in (vii) may be continued on annual renewal basis by the Authority beyond a period of one year.
ER , - , , 3 -,R/ -, 3
Chapter 8
8.0 Procedure for Obtaining Development Permission / Commencement Certificate.
8.1 Application : - Every person who intends to carry out development and erect, re-erect or make alterations in any place in a building or demolish any building, shall make an application in writing to the Authority of his intention in the prescribed form (See Annexure A1 or A2) and such application shall be accompanied by the payment receipt of required scrutiny fee and any other fee/ charges prescribed by the Authority from time to time and the plans and statements in sufficient copies (See Clause No. 8.1.1), as required under Clauses 8.2 and 8.3. The plans may be ordinary prints on Ferro paper or any other type (prints only), one set of plans shall be retained in the office of the Authority for record after the issue of Commencement Certificate or its refusal. For the sake of scrutiny, the plans may be submitted in a digital format (soft copy) as may be specified by the Authority from time to time.
8.1.1 Copies of Plans and Statements : - A minimum of four copies of plans and statements shall be made available along with the application. In the case of building schemes, where the clearance is required from other agencies like Fire Services and other authorities, the number of copies of plans required shall be as decided by the Authority.
Information Accompanying Application : - The application shall be accompanied by the key (location) plan, site plan, sub-division plan, layout plan, building plan, services plans, specifications and certificate of supervision and ownership title as prescribed below:
8.2.1 Size of drawing sheets, colouring of plans and Dimensions.
8.2.1.1 The sizes of drawing sheets shall be any of those specified in Table 1 below.
Table 1Drawing Sheet Sizes
Sr. No.
Designation
Trimmed Size, mm
(1)
(2)
(3)
1
AO
841 x 1189
2
A1
594 x 841
3
A2
420 x 594
4
A3
297 x 420
5
A4
210 x 297
Note : Submission of plans on sheets larger than A0 size is permissible.
(.f.y.)----3
RC ER T, T- a , T T , 3 3-, R0/ -, T 3
8.2.1.2 Colouring Notations for Plans : - The Plans shall be coloured as
specified in ‘Principal Regulations’. Prints of plans shall be on one side of paper.
Note : - For land development/ sub-division/ layout suitable colouring notations shall be used which shall be indexed.
8.2.1.3 Dimensions: All dimensions shall be indicated in metric units.
8.2.2 Ownership title and area : - Every application for development permission shall be accompanied by such of the following documents as may be relevant, for verifying the ownership and area etc. of the land: -
(a) 7/12 extract or property register card of a date not older than six months at the date of submission, attested copy of original registered deed for sale / lease / power of attorney etc. indicating ownership, whichever is applicable.
(b) A certified copy of the Measurement Plan of the property under development proposal.
(c) Statement of area of the holding by triangulation method from the qualified licensed technical person or architect with an affidavit from the owner about the area in the form prescribed by the Authority.
(d) Any other document prescribed by the Authority.
(e) Wherever a third party interest is created by way of agreement to sale or mortgage etc., the registered consent of such third party interests.
(f) A certified copy of approved sub-division / amalgamation / layout of land.
(g) In the case of leased land, the no-objection certificate of the Lessor.
(h) No-objection certificate from the ’ Developer ’.
8.2.3 Key Plan or Location Plan : - A key plan drawn to a scale of not less than 1:10,000 showing the boundary and location of the site with respect to neighbourhood landmarks.
8.2.4 Site Plan : - A site plan drawn to a scale not smaller than 1:500 and, where the plot is more than 10 hectares, to a scale not smaller than 1:2500, showing in addition the following details :
(a) Boundaries of the site along with disposition of contiguous land belonging to the owner and the position of site in relation to neighbouring streets ;
(b) The name of the street, if any, from which the building is proposed to derive access ;
R , , T , 3-, 2/ -,
(c) All existing buildings contained in the site with their names (where the buildings are given names) and their numbers;
(d) The position of the building and of other buildings, if any, which the applicant intends to erect, upon his land in relation to : -
(i) The boundaries of the site and, in a case where the site has been partitioned, the boundaries of the portions owned by others;
(ii) All adjacent streets, buildings (with number of storeys and height) and premises within a distance of 12 m. of the work site and of the contiguous land (if any) referred to in (a) above.
(e) The means of access from the street to the building and to all other buildings (if any) which the applicant intends to erect.
8.2.6.1 Building Plans for Multistoreyed and Special Buildings and Mixed
Occupancies : -
For the categories of buildings
(i) multistoreyed buildings which are more than 15m. height ;
(ii) special buildings for uses like educational, assembly, mercantile, institutional, industrial, storage and hazardous ;
(iii) mixed occupancies having area more than 500 sqm consisting of any one or more of the occupancies in (ii) above ;
in addition to the items (a) to (i) of Clause No. 8.2.6., following additional information shall be furnished and / or indicated in their Building Plans : -
R , , T , 3-, / -,
(a) access to fire appliances/ vehicles with details of vehicular turning circle and clear motorable access way around the building ;
(b) size (width) of main and alternate staircases along with balcony approach, corridor, ventilated lobby approach ;
(c) location and details of lift enclosures ;
(d) location and size of fire lift ;
(e) smoke stop lobby/door, where provided ;
(f) refuse chutes, refuse chambers, service ducts, etc .;
(g) vehicular parking spaces ;
(h) refuge area, if any ;
(i) details of building services :- air-conditioning system with position of fire dampers, mechanical ventilation system, electrical services, boilers, gas pipes etc .,
(j) details of exits including provision of ramps, etc. for hospitals and buildings requiring special fire protection measures,
(k) location of generator, transformer and switch gear room ;
(l) smoke exhauster system, if an y ;
(m) details of fire alarm system network ;
(n) location of centralized control, connecting all fire alarm systems, built in fire protection arrangements and public address system etc.
(o) location and dimensions of static water storage tank and pump room along with fire service inlets for mobile pump and water storage tank ;
(p) location and details of fixed fire protection installations such as sprinklers, wet risers, hose reels, drenchers, CO2 installation etc.;
(q) location and details of first aid, fire fighting equipments / installations.
(r) All provisions related to Active and Passive Fire Protection requirements adhering to Part 4 of National Building Code of India, 2005 i.e. Fire & Life Safety.
(s) Proof Checking of Structural Designs including Construction Process: The designs should be proof-checked by Proofing consultant appointed by the applicant. (The design consultant shall be required to submit all the design calculations and provide all necessary technical assistance in getting the designs proof checked). The Proofing Consultant shall also be responsible for proofing of maintenance of quality in construction process.
8.2.7. Service Plan : - Plans, elevations and sections of water supply, sewage disposal system and details of building services including rainwater harvesting, solar energy etc., as required by the Authority, shall be made available on a scale not less than 1:100 and for layouts at 1:1000.
8.7Commencement Certificate: Grant or Refusal to Grant
8 7.1 The Authority may either sanction or refuse the plans or may sanction them with such modifications or directions as it may deem necessary after having recovered the necessary charges and thereupon shall communicate its decision in the prescribed form to the person submitting the application for development.
8.7.2 (i) Special Buildings : The building plans for buildings identified in Clause No. 8.2.6.1 shall also be subject to the scrutiny of the Chief Fire Officer of the Special Planning Authority, and the Commencement Certificate shall be issued by the Authority.
(ii) Subdivision or Layout : In the case of land subdivision or layout, tentative layout shall be recommended in the form prescribed in Annexure ‘D-1’ for demarcation at first instance. After having demarcated the layout by the Land Records Department, the owner shall submit the demarcated layout for final approval to the Authority. If the demarcated layout is in accordance with the layout recommended for demarcation or is conforming to these Clauses, the Authority shall grant final approval in the form in Annexure ‘D-2’. The refusal to land subdivision or layout shall be communicated in the form in Annexure ‘D-3’.
8 7.3 Deemed Permission : If within sixty (60) days of receipt of the application along with necessary fees/ deposit under Clauses 8.2.10 and 8.2.11 of these provisions, the Authority fails to intimate the applicant in writing of its decision, the application with its plans and statements shall be deemed to have been sanctioned,
Provided that, no approval shall be construed to have authorised any person to do anything on the site of work in contravention with or against the terms of lease or title to the land.
Provided further that, the development proposal is strictly in conformity with the requirements of these provisions and byelaws or regulations framed in this behalf under any other law for the time being in force and the development proposal in no way violates any provisions of either draft or final Development Plans published by means of notice, submitted for sanction under the Act.
Provided also that, any development carried out in pursuance of such deemed permission which is in contravention of the provisions of the above provisos, shall be deemed to be an unauthorised development under the Act or other relevant Acts.
8.7.4 Once the plan has been scrutinised and objections have been pointed out, the owner submitting application shall modify the plan, comply with the objections raised and resubmit it. The prints of plans submitted for final approval, shall not contain superimposed corrections. The authority shall grant or refuse the commencement certificate within 60 days from the date of resubmission. No new
π ().f9.y.)----437
3E ER T, - a u, T , 3 3-99, R0/ 2R-, 993
objections may generally be raised when they are resubmitted after complying with earlier objections and without inserting new features.
8.8. Commencement of work : - Commencement Certificate/ development permission shall remain valid for one year from the date of its issue and, if the development has not commenced during that period, shall have to be renewed for another year. In any case, however, not more than three such annual renewals shall be permitted. However, there is no bar to obtain development permission afresh. The application for renewal shall be made before expiry of one year.
If application for renewal is made after expiry of one year, the Authority may condone the delay for submission of application for renewal by charging necessary fees.
For the purpose of this Clause, the word "Commencement" shall mean as has been specified in Table 2 below :-
Table 2What is Commencement?
Item No.
Item
Stage of Work
(a)
For a building work including additions and alterations
Up to plinth level.
(b)
For construction of bridges and overhead tanks
Foundation and work up to the base floor
(c)
For underground works
Foundation and work up to base of under ground floor.
(d)
For layout, sub-division and amalgamation
Final demarcation and complete provision of water bound macadam roads
8.9 Provision of Infrastructure: - In the case of land subdivision / group housing scheme, it shall be the responsibility of the owner to construct all infrastructure including roads, storm water drains, sewer lines, water supply lines, development of open spaces etc. within his land
In the case of land subdivision, these works shall be completed within two years and building permission shall be granted phase-wise depending upon the percentage of infrastructure work completed.
In the case of group housing scheme, these works shall be completed before completion of project.
(f) The space to be left around the building to secure free circulation of air, admission of light and access ;
(g) The width of the street (if any) in front and the street (if any) at the side or rear of the plot/ building ;
(h) The direction of north relative to the plan of the building ;
(i) Any existing physical features, such as wells, tanks, drains, pipelines, high tension lines, railway lines, trees, etc. ;
(j) The covered area of the whole property and the break-up of the covered area on each floor of every building ;
(k) A plan indicating parking spaces as required under these provisions;
(l) Overhead electric supply lines including space for electrical transformer / substation as per requirements of the electricity distribution company, water supply and drainage lines ;
(m) Such other particulars as may be prescribed by the Authority.
8.2.5 Sub-Division/ Layout Plan :- In the case of development of land, the sub-division/ layout plan drawn to a scale of not less than 1 : 500, or where land area exceeds 4 ha, to a scale of not less than 1 : 1000, containing the following :
(a) Scale used and the north direction ;
(b) Location of all proposed and existing roads within the land with their existing/proposed widths ;
(c) Dimensions of plots ;
(d) Location of drains, sewers, public facilities and services, electricity lines etc.
(e) Table indicating size, area and use of all plots in the sub-division / layout plan ;
(f) A statement indicating total area of the site, area utilized under roads, open spaces, play grounds, recreational open spaces and designations in the Development Plans like roads, schools, shopping
30 ER T, - , T , -, R0/ R-, 3
centres and other public amenities and facilities along with their percentage with reference to the total area of the site proposed to be sub-divided / laid out;
(g) In the case of built-up areas where plots are sub-divided, the means of access to the sub-division from existing streets.
8.2.6. Building Plan : - Wherever specified, building shall be designed to provide barrier-free environment for physically handicapped persons. The plans of the buildings with elevations and sections shall be drawn to a scale of 1:100 and shall
(a) include floor plans of all floors together with the covered area clearly indicating the sizes of rooms and the position and width of staircases, ramps and other exit ways, lift-wells, lift machine rooms and lift pit details. It shall also include ground floor plan as well as basement plans and shall indicate the details of parking spaces, loading and unloading spaces provided around and within building as also the access ways and the appurtenant open spaces with projections in dotted lines, distance from any building existing on the plot in figured dimensions along with accessory buildings ;
(b) show the use or occupancy of all parts of the building ;
(c) show exact location of essential services e.g. WC, sink, bath and the like ;
(d) include sectional drawings of the building showing all sectional details ;
(e) show all street elevations ;
(f) give dimensions of the projected portions beyond the permissible building line;
(g) include terrace plan indicating the drainage and the slopes of the roof, Rainwater Harvesting System, Solar Energy System where specified ;
(h) give indications of the north direction relative to the plans ; and
(i) give dimensions and details of doors, windows and ventilators ;
HERT T, - , T R, 3 3-, RO/ R-, T 3
8.2.8. Specifications - General specification of the proposed construction, giving type and grade of materials to be used in the form given in Annexure A-1, duly signed by Licensed Technical Person.
8.2.9. Certificate of Supervision : - A certificate of supervision by (i) the Licensed Technical Person in the Form no.2 of Appendix IX of the ’Principal Regulations and (ii) by Structural Engineer as prescribed in Annexure ‘B’ of these provisions. In the event of the said licensed technical person ceasing to be employed for the development work, the further development work shall stand suspended till a new licensed technical person is appointed.
8.2.10. Scrutiny Fee : - An attested copy of Receipt of payment of Scrutiny Fee. The Scrutiny Fee and layout /subdivision of land fees shall be as decided by the Authority from time to time subject to Government orders, if any.
8.2.11. Security Deposit Fee : - For ensuring faithful compliance with these Clauses and directions given in the sanctioned plan and other terms and conditions, a security fee shall be charged at rates as specified by the Authority. The same shall be returned to the owner after the issue of the full occupancy certificate to the building.
8.2.12 No Objection Certificate :- In the case of certain occupancies requiring clearance from authorities like Civil Aviation Authority, Railways, Directorate of Industries, Maharashtra Pollution Control Board, District Magistrate, Inspectorate of Boilers and Smoke Nuisance, Director of Fire Services etc., the relevant no objection certificates from these authorities, relevant to the occupancy.
8.2.13. Development Charge : - Before issue of development permission/ commencement certificate, development charge as required under the Act shall be deposited with the Authority by the plot holder in an Integrated Industrial Area. The Special Planning Authority shall maintain a Development Fund for implementing the provisions of section 124J of the Act and share it with the’Developer’ who is charged with the responsibility of development of infrastructure. The Special Planning Authority shall retain 10% of the proceeds of the Development Fund for administrative expenditure.
8.2.14. Premium for Hardship cases : - Premium as may be required to be recovered under these provisions shall be paid to the Authority before issue of development permission / commencement certificate.
8.2.15. Certificate of Clearance of Dues to the Authority : -A copy of a Certificate of Clearance of Dues to the Authority from the competent Department of the Special Planning Authority for payment of dues up to the date.
R , , T , 3-, 2/ -,
8.3. Signing of Plans : - All the plans shall be duly signed by the owner, co-owner, if any, and the Licensed Technical Personnel or Architect along with name, address and license number.
8.4 Qualification and Competence of the Licensed Technical Personnel : - Licensed Technical Personnel other than Architects referred to in Clause 8.3 shall be registered / licensed by the Authority. Architects and registered Licensed Technical Personnel shall be competent to plan and carry out various works as given in Annexure "C". The qualification and procedure for registration and licensing of the Licensed Technical Personnel shall be as given in Annexure- "C".
8.5 Proofing Consultant: - The person acting as a Proofing consultant shall be a person of repute in his field.