4.1 A land development/building project and the built facility during its service life comprises the following major stages:
a) Location/siting,
b) Conceptualization and planning,
c) Designing and detailing,
d) Construction/execution,
e) Operation and maintenance, and
f) Decommissioning and deconstruction.
Each stage necessarily requires professionals of many disciplines who should work together as a well coordinated team to achieve the desired product delivery with quality and safety and other objectives, in an effective manner.
Appropriate multi-disciplinary teams (see 4.1.1 to 4.1.3) need to be constituted to successfully meet the requirements of different stages. Each team may comprise need based professionals out of the following depending upon the nature, magnitude and complexity of the project:
-
Architect;
-
Civil engineer;
-
Structural engineer;
-
Geotechnical engineer;
-
Electrical engineer;
-
Plumbing engineer;
PART 0 INTEGRATED APPROACH — PREREQUISITE FOR APPLYING PROVISIONS OF THE CODE
-
Fire protection engineer;
-
Heating, ventilation and air conditioning engineer;
-
Lift, escalator and moving walk specialist;
-
Acoustics specialist;
-
Information/communication technology engineer;
-
Health, safety and environment specialist;
-
Environment/sustainability specialist;
-
Town planner;
-
Urban designer;
-
Landscape architect;
-
Security system specialist;
-
Interior designer;
-
Quantity surveyor;
-
Project/construction manager;
-
Accessibility and universal design specialist;
-
Asset/facility manager; and
-
Other subject specialist(s).
It is important that leaders and members of design team, project management/construction management team, and operation and maintenance team, depending on the size and complexity of the project, are carefully selected considering their qualification, experience and expertise in these fields.